Subsurface Utility Engineering (SUE) Investigation at Kennedy Station

Kennedy Station will be the terminal station at the eastern end of the LRT line, and will also serve as an interchange station. It will be located at Transway Crescent and Eglinton Avenue East, approximately 300 metres east of Kennedy Road.  Read more »

June 242016

Subsurface Utility Engineering (SUE) Investigation on Eglinton Avenue East at Leslie Street

In preparation for construction of the surface level section of the Eglinton Crosstown, crews will begin conducting preparatory activities and utility works including surveying, locating utilities, and drilling boreholes to obtain additional information on sub-surface utilities and ground conditions in various locations along Eglinton.

What work is starting? Read more »

June 232016

Tunnelling: What You May Experience

As you may know, the Eglinton Crosstown includes a 10-kilometre underground portion, between Keele Street and Laird Drive. For the tunnelled portion, locomotives run along interim track and transport materials and haul spoils in and out of the tunnels to the extraction shafts. Tunnel boring machines (TBMs) and muck removal operations run around the clock - 24 hours a day. Read more »

June 222016

Eglinton Park

We met with the community on June 21 to discuss the use of a portion of Eglinton Park for building the future Avenue station. Here is the presentation if you missed us: Read more »

June 222016

Mount Pleasant Dewatering to Commence Week of June 20, 2016

What work is starting?

What: Dewatering will commence to allow crews to perform scheduled maintenance on the tunnel boring machines. Dewatering wells were installed in advance of the arrival of the tunnel boring machines.  Read more »

June 212016

Utility Relocations at Laird Station

What work is Taking Place?

  • Pending a City of Toronto permit, work will commence to relocate existing Bell utilities at the southwest corner of Eglinton Avenue East and Laird Drive and to make way for the future Laird station.

Timing Read more »

June 172016

Enbridge Gas Distribution Line Relocation for Science Centre Station

What work is Taking Place?

  • To accommodate the new Eglinton Crosstown, Enbridge is required to relocate a gas line.
  • Work will start as early as June 20, 2016 and last for approximately six weeks.

Timing Read more »