June 172016

Enbridge Gas Distribution Line Relocation for Science Centre Station

What work is Taking Place?

  • To accommodate the new Eglinton Crosstown, Enbridge is required to relocate a gas line.
  • Work will start as early as June 20, 2016 and last for approximately six weeks.

Timing Read more »

June 152016

South Eglinton Avenue Sidewalk Restoration at Mount Pleasant Road

What work is starting?

What: Following the completion of headwall construction, crews will restore the sidewalk on the south side of Eglinton Avenue East.

Why: This restoration work is required to return the Mount Pleasant Road and Eglinton Avenue intersection to its original condition after headwall construction, completed in early 2016 for the future Mount Pleasant station.  Read more »

June 132016

Road Restoration on Eglinton Avenue East, west of Mount Pleasant Road

What work is starting?

What: Following the completion of Mount Pleasant headwall work, road surface restoration is required on Eglinton Avenue East, west of Mount Pleasant Road to Brownlow Avenue.

When: Starting approximately from Tuesday, June 14, 2016 until approximately Friday, June 17, 2016.

Where: Crews will be working in the middle lanes on Eglinton Avenue East, west of Mount Pleasant Road to Brownlow Avenue. Read more »

June 132016

Road Restoration on Eglinton Avenue East, west of Mount Pleasant Road

What work is starting?

What: Following the completion of Mount Pleasant headwall work, road surface restoration is required on Eglinton Avenue East, west of Mount Pleasant Road to Brownlow Avenue.

When: Starting approximately from Tuesday, June 14, 2016 until approximately Friday, June 17, 2016.

Where: Crews will be working in the middle lanes on Eglinton Avenue East, west of Mount Pleasant Road to Brownlow Avenue.

June 132016

Restoration work at Eglinton Avenue East and Bayview Avenue

What work is starting?

What: Bayview Station headwall work is complete. Crews will begin the following restoration work:

  • Restoring the sidewalk on the south side of Eglinton Avenue East, east of Bayview Avenue.
  • Restoring hydro poles and overhead wires to their original locations, on the south side of Eglinton Avenue East, west of Bayview Avenue.

Why:    Read more »

June 132016

Overnight Construction at Bayview and Eglinton Intersection

What work is starting?

What: Removal of the jet-grout delivery trench and road surface restoration within the intersection of Bayview Avenue and Eglinton Avenue East.

When: Wednesday, June 15, 2016 at 9:00 p.m. to Thursday, June 16, 2016 at 5:00 a.m.

Where: Crews will be working within the intersection at Bayview Avenue and Eglinton Avenue East.   Read more »

June 102016
June 072016

Update: Emergency Exit Building Construction near Petman Avenue Work Shifts to North Side of Eglinton Avenue East for Utility Relocation

What work is Taking Place?

What: With utility work and secant piling installations on the south side of Eglinton complete, work will return to the north side of Eglinton at Petman. During this stage, crews will continue to relocate utilities. 

Why: Construction of emergency exit buildings requires utilities to be safely relocated. Depending on site conditions, this could include moving gas, hydro, water mains, sewers, and telephone lines, traffic lights and street lighting.  Read more »