Construction Updates

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

Syndicate content
 
June 122020

UTILITY CROSSING AT DON MILLS ROAD, EAST SIDEWALK

UTILITY CROSSING AT DON MILLS ROAD, EAST SIDEWALK

 

WHAT WORK IS TAKING PLACE? Read more »

June 122020

Crane Erection on Vaughan Road at Fairbank Station - June 15, 2020

What Work is Taking Place?

On Monday June 15, 2020, crews will install a crane on Vaughan Road adjacent to the Fairbank Station Main Entrance site. The crane will remain in place for approximately two weeks to assist with lifting and hoisting activities at the future station’s Main Entrance. Read more »

June 112020

Elevator Construction at Eglinton Station

 

What Work is Taking Place?

In June 2020, crews will begin construction of a new elevator inside of 2200 Yonge Street (former Smoke’s Poutinerie). The elevator will service the existing TTC Eglinton Station. Using a saw cutter, core drill and jack hammer, the existing concrete will be demolished. Demolition work will take approximately two weeks to complete. Once demolition work is complete, construction of the new elevator will begin.

 

Hours of Work Read more »

June 112020

Shelter Installation at Aga Khan Park & Museum Stop South Platform

Shelter Installation at Aga Khan Park & Museum Stop

What Work is Taking Place?  Read more »

June 112020

Road Widening and Reconstruction Eglinton Avenue East at Brentcliffe Road – South Side

ORIGINAL POST: MAY 8, 2020

UPDATED: JUNE 11, 2020

 

Road Widening and Reconstruction Read more »

June 102020

Lane Reduction for Concrete Pour at Caledonia Station - June 11, 2020

What Work is Taking Place?

On Thursday, June 11, crews at Caledonia will be pouring concrete to form a street level slab in the future station’s Main Entrance. During the pour, westbound Eglinton Ave W will be reduced to one (1) lane only between Blackthorne Ave and Gabian Way. Lane reductions will begin as early as 7:00am and last for approximately six (6) hours.

 

Hours of Work Read more »

June 092020

Update: Notice of Chipping at Chaplin Station June 9 – June 13, 2020

What work is Taking Place?

In late May 2020, crews began chipping a concrete wall located between the Chaplin Station Tertiary Entrance and the station box.  This work will continue from June 9 through June 13, 2020 between the hours of 7:00 a.m. – 11:00 p.m.  Chipping is the process of using an excavator and jackhammer to remove concrete and hardened material. Chipping occurs periodically as deep excavation progresses.  Noise and vibration can be expected.

Hours of Work Read more »

June 082020

Extended Construction Hours for Excavation and Tunnel Demolition at Mount Pleasant Station - Summer 2020

 

What Work is Taking Place?

Deep excavation has been underway at Mount Pleasant Station since February 2020.  Crews are currently excavating the station box beneath Eglinton Avenue. Soil is being removed through the Secondary Entrance located on the north side of Eglinton Avenue, between Mount Pleasant Road and Rawlinson Avenue. In June 2020, crews will begin to demolish the tunnels beneath Eglinton Avenue to make way for construction of the station underground.  Read more »