Construction Updates

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

Syndicate content
 
July 172015

Gas line relocation for future Caledonia Station Starting the week of August 4, 2015

What work is starting?

What: Enbridge Gas Distribution will be relocating natural gas pipelines at the site of the future Caledonia Station.

Map - Enbridge work Caledonia July 2015 Read more »

July 152015

UPDATE: Avenue Station Headwall Construction

What: In this phase of construction, crews are building the headwalls for the future Avenue Station. Headwalls are underground support walls located at the east and west ends of the station location.  Read more »

July 152015

Gas line relocation for future Chaplin Station Starting the week of August 4, 2015

What work is starting?

What: Enbridge Gas Distribution will be relocating natural gas pipelines at the site of the future Chaplin Station.

Map - Chaplin gas relocation July 2015 Read more »

July 062015

Update: Emergency Exit Building Construction near Petman Avenue Utility Relocation Work Moves to South, then North Side of Eglinton Avenue East

Emergency exit buildings (EEBs) are built in between stations when station platforms are more than approximately 760 metres apart to allow for easy evacuation of passengers. The construction of an EEB includes the building of an evacuation pathway, a set of stairs from the tunnel to ground level, and a small building the surface. The scale of construction is similar to building a small-scale underground station. Generally, it takes up to 24 months to complete construction at each EEB.

What work is starting? Read more »

July 022015
June 262015

Setup of Jet Grout Plant on Eglinton Avenue East between Dunfield Avenue and Redpath Avenue

SEE VIDEO

What work is starting?

What: Crews will setup a jet grout plant on the north side of the roadway on Eglinton Avenue East between Dunfield Avenue and Redpath Avenue. Read more »

June 252015

Toronto Hydro Utility Overhead Relocation Work at Mount Pleasant and Eglinton

What work is starting?

What: Toronto Hydro crews will relocate overhead Hydro utilities at the intersection of Mount Pleasant Road and Eglinton Avenue East ahead of headwall construction for the future Mount Pleasant Station.  Read more »

June 232015

Construction Delays at Bathurst Street and Avenue Road

Dear Neighbours,

We understand and appreciate that you have endured our construction activities for months already and will have to endure it for many more months to come.  We regret the inconvenience that construction causes as we build the Eglinton Crosstown LRT project.  Read more »

June 192015

Overnight Work at Miranda Avenue

Dear Neighbours,

Crews will be working into the night on Friday June 19, 2015 in order to complete critical work in this work zone ahead of the Fairbank Village Multicultural Festival this weekend.

We apologize for the inconvenience.

Regards,

Carlos, Stas, Lancefield and Chasya

Crosstown Community Office

June 122015

Update: Eglinton Avenue East Extraction Shaft Work In North Lanes

What: Work continues at the extraction shaft on Eglinton Avenue between Yonge Street and Lillian Street. The next stage of work is set to begin, which will remain on the north lanes of Eglinton Avenue. This work will include, heavy civil construction; installation of secant piles, jet grouting, daylighting and relocating utilities. Read more »