August 212015

Partial Road Closure for Gilgorm Road

Starting the week of August 24, 2015

What work is starting?

What: Enbridge Gas Distribution (Enbridge) will need to close the south end of Gilgorm Road (at Eglinton Avenue West) in order to complete the relocation of natural gas pipelines.

partial road closure gilgorm august 2015 Read more »

August 202015

Update - Mount Pleasant Headwall Construction on the North Side of Eglinton

What phase of work is starting in the vicinity of Mount Pleasant Road? 

What:  Crews will build the Mount Pleasant headwall on the north side of Eglinton Avenue East, east and west of Mount Pleasant Road, for the future Mount Pleasant Station in advance of tunnel construction. Headwalls are underground support walls located at the east and west ends of the station location.   Read more »

August 182015

Active Truck Staging Lane and Construction Compound

What: Both Tunnel Boring Machines have started tunnelling east of Allen Road to Yonge Street. The southbound Allen Road truck staging lane will be used to hold up to 4 trucks at a time as part of the operations. Additionally, the construction compound on the northbound Allen Road will be used as full time facility for staff and crews.   Read more »

August 182015

The Fairbank Neighbourhood

The Fairbank neighbourhood is a reverse L-shape that stretches from Eglinton Avenue West between Chamberlain Avenue and Dufferin Street.

The Fairbank Village Business Improvement Area (BIA) was established in 2007 and it currently has more than 120 members.

Fairbank map Read more »

August 172015

Overnight Restoration Work Wednesday and Thursday 9 pm to 6 am, on Eglinton between Chaplin & Latimer

What: Crews will be completing restoration of the roadway overnight in an effort to minimize traffic impacts. Noise and asphalt smell can be expected as part of this work.

When: August 15 and 16 from 9 p.m. in the evening to 6 a.m. in the morning.

Where: This work will take place on Eglinton Avenue between Chaplin Crescent and Latimer Avenue. Read more »

August 172015

Monitoring Equipment Installation along Eglinton Avenue East at Avenue Road

What: Monitoring equipment will continue to be installed at major intersections along Eglinton Avenue East. This equipment will measure important data related to the work of our tunnel boring machines underground. These measurements will allow construction crews to adjust tunnelling activities along Eglinton Avenue East if needed.   Read more »

August 142015

Overnight Restoration Work - Monday August 15 and Tuesday August 16

What: Crews will be completing restoration of the roadway overnight in an effort to minimize traffic impacts.  Noise and asphalt smell can be expected as part of this work.

When: August 15 and 16 from 9 p.m. in the evening to 6 a.m. in the morning.

Why: Construction of underground headwalls for the future Bathurst Station is nearing completion. Crews will be restoring the intersection to pre-construction conditions.  Read more »

August 112015

Toronto Hydro Utility Overhead Relocation Work at Bayview and Eglinton - Stage Two

What work is starting?

What: Toronto Hydro crews will be relocating overhead hydro utilities at the intersection of Bayview Avenue and Eglinton Avenue East ahead of headwall construction for the future Bayview Station.  Read more »

August 072015

Enbridge Gas Line Relocation - An Update

Dear neighbours, 

As you are aware, Enbridge Gas Distribution (Enbridge) has been relocating natural gas pipelines at the site of the future Oakwood Station. These pipelines are integral to Enbridge’s gas system and must be re-routed to ensure the safe and reliable delivery of natural gas to customers in the Greater Toronto Area. The work has involved relocating a gas pipeline to Times Road, Livingstone Avenue and Marlee Avenue.  Read more »

July 292015

Update – Toronto Hydro Overhead Relocation Work at Mount Pleasant and Eglinton

What work is starting?

What: Toronto Hydro crews will be relocating overhead hydro utilities at the intersection of Mount Pleasant Road and Eglinton Avenue East ahead of headwall construction for the future Mount Pleasant Station.   Read more »