Demolition Work at Future Leaside (formerly Bayview) Station

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

 
March 2, 2016

What work is starting?

In February 2016, crews began conducting preparatory activities in the Bayview Avenue and Eglinton Avenue East vicinity to make way for the future Leaside Station. 

Upcoming Works – Demolition

  • One commercial property located at 1787 Bayview Avenue will be demolished to make way for Leaside Station. 
  • For safety purposes, temporary fencing and hoarding will be installed around the demolition site.

Timing

  • Demolition work will last for approximately four (4) weeks and is expected to begin the week of March 14th, 2016.
  • Demolition work will take place between the hours of 7:00 a.m. and 7:00 p.m.

What to expect

  • Residents and businesses near demolition sites should anticipate noise from excavators, bobcats, and other construction equipment as well as dust caused by demolition activity and removal of debris.
  • Some street furniture in the vicinity will also be removed including a newspaper mailbox.

Traffic Impacts

  • Road closures are not anticipated for demolition works.
  • Sidewalk and property access will be maintained.

Please Contact Us

If you would like more detail about this work or any other aspect of the Eglinton Crosstown project, please do not hesitate to contact Nicole DiCarlo at (416) 482-7411. We thank you for your continued patience as we work to build rapid transit.

 

The Eglinton Crosstown is a 19-kilometre light rail transit (LRT) line that will run along Eglinton Avenue through the heart of Toronto, with an underground central section. The line will connect Mount Dennis in the west to Kennedy Road in the east, and the new service will be up to 60% faster than the bus service today.

Please support your local businesses during construction.