November 8, 2019

What Work is Taking Place?

Starting November 4, 2019, crews began installing several dewatering wells in the vicinity of Bathurst Street and Eglinton Avenue West, as part of the construction of Forest Hill Station.  Dewatering wells form part of the system that removes ground water during excavation.  This work will take place overnight between 9:00 p.m. – 5:00 a.m.  During each shift, sidewalk interruptions may be in effect on the north side of Eglinton Ave between the Secondary Entrance and Bathurst St. 

Details

  • Monday November 4 – 15, 2019 between 9:00 p.m. and 5:00 a.m., excluding weekends
  • Work may be rescheduled due to inclement weather or unforeseen circumstances

Construction Staging

Traffic Configuration during Dewatering Well Installation work at Forest Hill Station, November 4 to 15

What to Expect

  • Overnight noise from drilling activity, as well as ongoing excavation work, can be expected
  • Site lighting can be expected
  • Sidewalk interruptions on the north side of Eglinton Ave between Bathurst St and the Secondary Entrance; pedestrians may experience delays when travelling through the area or be directed to use the south sidewalk
  • Property access will be maintained
  • No changes to the current traffic configuration are expected

 

 

Disponible en français.

Thank you for your continued patience as we work to build this important project.

Please support your local businesses during construction.

Sign up at www.thecrosstown.ca/sign-up to receive regular email updates.