Dufferin Street

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

Syndicate content
 
February 162018

Fairbank-Oakwood Construction Liaison Committee Meeting

he construction liaison committee meeting of Fairbank and Oakwood stations was held on February 15, 2018. You can see the presentation here:

Read more »

February 162018

Overnight Wet Utilities Relocation at Fairbank Station

WHAT WORK IS TAKING PLACE?

In late October, crews began wet utilities relocation in the vicinity of Dufferin Street and Eglinton Avenue West to make way for support of excavation (shoring) activities on the north and south sides of Eglinton Avenue West.  

Work on the combined sewer is continuing and requires additional short-term lane occupancy on Eglinton Ave and Dufferin St.   Read more »

January 252018

Temporary Pedestrian Change at Fairbank Station

WHAT WORK IS TAKING PLACE?

  • To accommodate wet utilities work on the southwest corner of the intersection, a change to the pedestrian crossing at Dufferin Street and Eglinton Avenue West has been implemented.  
  • The south crosswalk is closed and the west, east and north crosswalks are open.  
  • The temporary condition will be in place for approximately one (1) week.  
  • Upon completion, the south sidewalk will be reinstated and the east crosswalk will be closed again.

DETAILS Read more »

January 252018

Traffic and Pedestrian Changes at Fairbank Station - February 2018

WHAT WORK IS TAKING PLACE?

In late January, piling on the north side of Eglinton Avenue West will be complete and crews will move to the south side of Eglinton Avenue West to begin support of excavation activities, including piling, shallow excavation and roof slab construction.  This work will take place in several stages over a period of approximately eight (8) months.  In late 2018, crews will return to the north side of Eglinton Ave W to complete shallow excavation and roof slab construction. Read more »

November 172017

Overnight Water Utilities Relocation Work

What Work is Taking Place?

In late October, crews began relocating an existing watermain in the vicinity of Dufferin Street, Eglinton Avenue West and Vaughan Road to make way for support of excavation (shoring) activities on the north and south sides of Eglinton Avenue West.  Read more »

November 032017
October 192017

Traffic Change at Fairbank Station - October 2017

What Work is Taking Place?

Since fall 2016, crews have been conducting support of excavation work (also known as shoring) at the Main Entrance and Service Building sites of the future Fairbank Station.  In the spring, crews began shoring of the station box, as well as wet utilities relocation, on the north side of Eglinton Avenue West. Read more »