Dufferin Street

Looking for updates near a specific intersection?

Choose an intersection from the drop down list to view all of the latest news and construction updates in that area. Intersections are listed from west to east with Eglinton as the main cross-street.




Syndicate content
 
March 142017

Shoring at Fairbank Station Service Building

What Work is Taking Place?

Beginning in mid-March 2017, crews will start support of excavation work, also known as shoring, at the future Fairbank Station Service Building.  The Service Building is located on the southwest corner of Eglinton Avenue West and Dufferin Street, and will be used to host mechanical and electrical equipment for the station.   Read more »

March 032017

Subsurface Utility Engineering Investigation at Fairbank Station

What Work is Taking Place?

Beginning in March 2017, crews will begin subsurface utility engineering at the future Fairbank Station, in which boreholes will be drilled into the roadway in order to investigate underground utilities and ground conditions in advance of wet utilities relocation.  This work will take place throughout the vicinity of Eglinton Avenue West and Dufferin Street.  Read more »

February 082017

Gas Line Distribution Work at Fairbank Station

What Work is Taking Place?

  • To accommodate the new Eglinton Crosstown, Enbridge is required to relocate a gas line in the area of Dufferin Street and Eglinton Avenue West.
  • Work will start in February and last for approximately two weeks

Enbridge Work Read more »

February 032017
November 292016

Shoring and Guide Wall Construction at Fairbank Station Main Entrance

What Work is Taking Place? 

Beginning in late November 2016, crews will start support of excavation work, also known as shoring, at the future Fairbank Station.  The main entrance is located on the southeast corn Read more »

November 032016

Overnight Rogers Utility Relocation Work at Fairbank Station

Overnight Rogers Utility Relocation Work at Fairbank Station

What Work is Taking Place?

Since September 2016, crews have been relocating existing telecommunications (Rogers) utilities in the vicinity of Eglinton Avenue West and Dufferin Street in preparation for station construction. Read more »

October 062016

Backfilling and Compaction at Fairbank Station

What Work is Taking Place?

Crews will begin backfilling and compaction work at the main station entrance site of the future Fairbank Station.  This work involves refilling and leveling the demolition site with fresh granular material, compaction of the material into the ground, and construction of the crane and drill rig pad.  This activity will prepare t Read more »

September 062016

Pedestrian Safety near Construction Sites

Construction of the Eglinton Crosstown LRT line, including 15 underground stations, is underway. Since the end of school, many construction sites have been set up for station construction and the set-up of some major intersections along Eglinton Avenue has been changed.

Pedestrian Information Read more »