Dufferin Street
Looking for information related to a specific area?
Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).
- Allen Road
- Avenue Road
- Bathurst Street
- Bayview Avenue
- Bermondsey Road
- Birchmount Road
- Black Creek Drive
- Brentcliffe Road
- Caledonia Road
- Chaplin Crescent
- Don Mills Road
- Donlea Drive/Hanna Road
- Don Valley Parkway (DVP)
- Dufferin Street
- Ferrand Drive
- Ionview Road
- Keele Street
- Kennedy Road
- Laird Drive
- Leslie Street
- Lebovic Avenue
- Little Blvd.
- Mount Pleasant Road
- Oakwood Avenue
- Petman Avenue
- Pharmacy Avenue
- Victoria Park Avenue
- Warden Avenue
- Weston Road
- Wynford Drive
- Yonge Street

Lane Reduction for Road Repair at Fairbank Station - July 14, 2020
What Work is Taking Place?
On Tuesday July 14, crews at Fairbank will conduct road repairs east of Dufferin Street on Eglinton Avenue West. To complete this work, Eglinton Avenue West, east of Dufferin Street, will be reduced to one lane; for this portion of Eglinton Ave West, two-way traffic will be controlled by traffic control personnel and Paid Duty Officers. The lanes will be reduced from as early as 10:00 a.m. – 2:00 p.m.
Hours of Work Read more »
UPDATED: Upcoming Concrete Pours at Fairbank Station - July 9, 10, 15, & 17, 2020
*Updated on July 14 - the concrete pour scheduled for July 15 has been cancelled*
What Work is Taking Place? Read more »
CANCELLED: Overnight Lane Reductions for Watermain Connections at Fairbank Station - July 6 to 10, 2020
*This work has been CANCELLED UNTIL FURTHER NOTICE as of June 30, 2020*
What Work is Taking Place? Read more »
Large Concrete Pour at Fairbank Station - June 25, 2020
What Work is Taking Place? Read more »
Concrete Pour at Fairbank Station - June 24, 2020
What Work is Taking Place?
On Wednesday June 24, crews will perform a concrete pour to form a wall at track level. Work will begin as early as 6:00am and the pour will be ongoing for approximately 12 hours. Concrete pumps will be placed within the secondary entrance work zone on the northwest corner of the intersection. Concrete trucks will be staged on Eglinton Avenue W, west of Shortt St. Dufferin St and Eglinton Ave W will remain open while work takes place.
Hours of Work Read more »
Lane Reduction for Watermain Works at Fairbank Station - June 17, 2020
What Work is Taking Place? Read more »
Concrete Pour at Fairbank Station - June 12, 2020
What Work is Taking Place? Read more »
Crane Erection on Vaughan Road at Fairbank Station - June 15, 2020
What Work is Taking Place?
On Monday June 15, 2020, crews will install a crane on Vaughan Road adjacent to the Fairbank Station Main Entrance site. The crane will remain in place for approximately two weeks to assist with lifting and hoisting activities at the future station’s Main Entrance. Read more »
Lane Reduction for Watermain Works at Fairbank Station - June 10, 2020
What Work is Taking Place? Read more »
Temporary Work Zone Extension at Fairbank Station: June 8 - July 3, 2020
*updated June 1 & June 22