September 10, 2019

 

EARLY MORNING CONCRETE POURS: CELESTICA BRIDGE AND DON VALLEY PARKWAY WEST

WHAT WORK IS TAKING PLACE?

As part of continued guideway construction on Eglinton Avenue East, two early morning concrete pours will take place this week. A concrete pour will occur as early as 5:00 a.m. on September 10th, 2019 on Eglinton Avenue East between the CP Rail Bridge and the Celestica Bridge and at the Don Valley Parkway West ramps on September 11th, 2019 at 5:00 a.m.

All works are in support of the construction of the Crosstown LRT tracks and guideway (dedicated transit lane) in the centre of Eglinton Avenue East.


 TIMING

  • Early morning concrete pours will take place on September 10th and September 11th as early as 5:00 a.m.
  • The contractor may not always work during the permitted hours, but may do so at its discretion. Work may be rescheduled due to weather conditions or unforeseen circumstances.

WHAT TO EXPECT

  • Temporary lane reductions may be required with a minimum of one through lane of traffic in each direction maintained.
  • There may be occurrences where a shoulder is narrowed and/or a traffic protection barrier is placed to accommodate safe working conditions.