Eglinton Maintenance & Storage Facility: Sanitary Connection

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

 
August 21, 2017

What Work is Taking Place? 

As part of the ongoing construction of the Eglinton Maintenance & Storage Facility (EMSF) crews will be working within the southbound lane of Industry Avenue. Once this work is completed the work will flip to the northside to access the manhole on the opposite side.

Work Zone on Industry

  • Work will occur over a period of two weeks, beginning on August 24, 2017.
  • This work will occur between the hours of 7:00 a.m. and 5:00 p.m. daily
  • If overnight work is required, we will notify the public in advance and monitor activities throughout
  • Work may be rescheduled due to weather conditions or unforeseen circumstances.

 

What to Expect

  • Nearby businesses can expect to hear noise form vacuum trucks and other construction equipment caused by utilities relocation activities.

 

Traffic and Pedestrian Impacts

  • Lane will be closed in work area with flagmen on site to direct traffic.
  • Sidewalks will remain open during this work.
  • Access to businesses will be maintained.

For more information, please contact Lancefield Morgan at the West Community Office 416 782-8118 or crosstown@metrolinx.com

Thank you for your continued patience as we work to build this important project.

Please support your local businesses during construction.

 

Sign up at www.thecrosstown.ca/sign-up to receive regular email updates.