What's New?
Looking for information related to a specific area?
Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).
- Allen Road
- Avenue Road
- Bathurst Street
- Bayview Avenue
- Bermondsey Road
- Birchmount Road
- Black Creek Drive
- Brentcliffe Road
- Caledonia Road
- Chaplin Crescent
- Don Mills Road
- Donlea Drive/Hanna Road
- Don Valley Parkway (DVP)
- Dufferin Street
- Ferrand Drive
- Ionview Road
- Keele Street
- Kennedy Road
- Laird Drive
- Leslie Street
- Lebovic Avenue
- Little Blvd.
- Mount Pleasant Road
- Oakwood Avenue
- Petman Avenue
- Pharmacy Avenue
- Victoria Park Avenue
- Warden Avenue
- Weston Road
- Wynford Drive
- Yonge Street
Shoring at Fairbank Station Service Building
What Work is Taking Place?
Beginning in mid-March 2017, crews will start support of excavation work, also known as shoring, at the future Fairbank Station Service Building. The Service Building is located on the southwest corner of Eglinton Avenue West and Dufferin Street, and will be used to host mechanical and electrical equipment for the station. Read more »
UPDATE: Shoring and Excavation Work for Avenue Station
Update
Based on consultations with local residents and businesses as well as elected officials, the following amended staging plan has been prepared and will be implemented as soon as March 13, 2017.
What changed?
The pedestrian walkway in front of the Secondary Entrance construction area will be closed. There will be no continuous travel on the north side of Eglinton Ave between Lascelles Blvd and Avenue Road. To access businesses on the east side of the secondary entrance, please use the crossing at Oriole Parkway. Read more »
UPDATE: Construction Staging in Eglinton Park
What Work is Taking Place?
In late 2016, a portion of the western frontage of Eglinton Park was fenced off to accommodate construction staging. Through consultations with the public and local elected officials, a reduced portion of the Eglinton Park was approved for temporary use during the construction of the Eglinton Crosstown. Read more »
UPDATE: Ongoing Utility Relocations and Site Service Connections at Laird Station
What Work is Taking Place? Read more »
Thank-you and farewell to the Crosstown’s TBMs!
The Eglinton Crosstown light rail transit (LRT) project marks another significant milestone the week of March 13th, 2017. Metrolinx will start the process of extracting the tunnel boring machines (TBM) from the completed east tunnels, and say farewell to our faithful helpers, TBM Don and TBM Humber.
What is happening?
The TBMs will be disassembled and lifted from extraction shaft just east of Yonge & Eglinton in four over-sized sections over four days. TBM Don, the machine that bored the north tunnel, will be removed first. Read more »
CORRECTION: Unplanned Utilities Work at Oakwood Station
What Work is Taking Place?
Over the next two (2) weeks, crews will complete work on sewer utility on Eglinton Ave W between Oakwood Ave and Times Road. During this work the Green P will be open, however access from Eglinton Ave will be closed. Read more »
Leaside Station Open House
Thank you for attending our Leaside station Open House on March 7, 2017.
For those of you who missed it, the presentation is here:
UPDATE: Traffic reconfiguration in support of excavation works and utility relocations for Science Centre Station
What Work is Taking Place?
As part of the continued support of excavation works and utility relocations for the future Science Centre station, traffic staging at the intersection of Don Mills Road and Eglinton Avenue East was reconfigured in mid-February 2017. This new set up will remain in place for up to three (3) months. Read more »