March 14 2017

Shoring at Fairbank Station Service Building

What Work is Taking Place?

Beginning in mid-March 2017, crews will start support of excavation work, also known as shoring, at the future Fairbank Station Service Building.  The Service Building is located on the southwest corner of Eglinton Avenue West and Dufferin Street, and will be used to host mechanical and electrical equipment for the station.   Read more »

March 13 2017

UPDATE: Shoring and Excavation Work for Avenue Station

Update

Based on consultations with local residents and businesses as well as elected officials, the following amended staging plan has been prepared and will be implemented as soon as March 13, 2017.

What changed?

The pedestrian walkway in front of the Secondary Entrance construction area will be closed. There will be no continuous travel on the north side of Eglinton Ave between Lascelles Blvd  and Avenue Road. To access businesses on the east side of the secondary entrance, please use the crossing at Oriole Parkway.  Read more »

March 13 2017

UPDATE: Construction Staging in Eglinton Park

What Work is Taking Place?

In late 2016, a portion of the western frontage of Eglinton Park was fenced off to accommodate construction staging. Through consultations with the public and local elected officials, a reduced portion of the Eglinton Park was approved for temporary use during the construction of the Eglinton Crosstown.   Read more »

March 10 2017

Thank-you and farewell to the Crosstown’s TBMs!

The Eglinton Crosstown light rail transit (LRT) project marks another significant milestone the week of March 13th, 2017. Metrolinx will start the process of extracting the tunnel boring machines (TBM) from the completed east tunnels, and say farewell to our faithful helpers, TBM Don and TBM Humber. 

What is happening?

The TBMs will be disassembled and lifted from extraction shaft just east of Yonge & Eglinton in four over-sized sections over four days. TBM Don, the machine that bored the north tunnel, will be removed first. Read more »

March 09 2017

CORRECTION: Unplanned Utilities Work at Oakwood Station

What Work is Taking Place?

Over the next two (2) weeks, crews will complete work on sewer utility on Eglinton Ave W between Oakwood Ave and Times Road.  During this work the Green P will be open, however access from Eglinton Ave will be closed.  Read more »

March 08 2017

Leaside Station Open House

Thank you for attending our Leaside station Open House on March 7, 2017.

For those of you who missed it, the presentation is here:

Read more »

March 07 2017

UPDATE: Traffic reconfiguration in support of excavation works and utility relocations for Science Centre Station

What Work is Taking Place?

As part of the continued support of excavation works and utility relocations for the future Science Centre station, traffic staging at the intersection of Don Mills Road and Eglinton Avenue East was reconfigured in mid-February 2017. This new set up will remain in place for up to three (3) months. Read more »