July 27 2020

Laird Station 24-Hour Concrete Pour

What Work is Taking Place?
Beginning July 29, 2020, crews will perform a 24-hour concrete pour at the main entrance at Laird Station. Work will begin preparatory work as early as 5:00 a.m. and the pour will be ongoing for approximately 24 hours.  

  Read more »

Categories:
July 24 2020

*UPDATED* Concrete Pour at Allen Road and Eglinton Avenue West - July 31-August 1, 2020

*Details for this work were updated on July 28, 2020

Upcoming Concrete Pour at Allen Road and Eglinton Avenue West July 31, 2020

What Work Is Taking Place? Read more »

July 24 2020

TEMPORARY TRAFFIC SIGNAL OUTAGE

What Work is Taking Place?
On July 27, 2020, crews will be performing repairs to an underground hydro chamber near the Eglinton Ave E and Leslie St intersection. To perform these repairs a temporary traffic signal outage will be required. Traffic will be controlled by paid duty officers at the intersection.
Hours of Work
• Work will begin at 8:00 a.m. on July 27, 2020 and continue for a maximum of four (4) hours. 
• In the event of inclement weather or unexpected circumstances, this work may be rescheduled. Read more »

Categories: