October 05 2016

Geotechnical Monitoring and Instrumentation Works at Eglinton Station

What Work is Taking Place?

  • Crews will drill several boreholes in the Eglinton Station area to install monitoring equipment that measures settlement or movement in the existing structures during the forthcoming shoring (support of excavation).
  • Work will take place intermittently along Eglinton Avenue, Yonge Street, Cowbell Lane, Holly Street, Duplex Avenue, and Berwick Avenue, as crews move from one borehole to the next.

Timing Read more »

October 04 2016

Upcoming Overnight Works at Eglinton Station: Signal Reconfigurations and Traffic Staging

 

What Work is Taking Place?

Pending permits and approvals, work will commence to reconfigure the traffic lights and introduce traffic staging at the Yonge-Eglinton intersection to prepare for upcoming utilities relocations.

Timing Read more »

October 01 2016

Subsurface Utility Engineering (SUE) Investigations at Eglinton Station

What work is Taking Place?

  • To prepare for future construction of Eglinton Station, crews will be conducting Subsurface Utility Engineering (SUE) investigations along Eglinton Avenue between Duplex Avenue and Holly Street.
  • Crews will drill bore holes and use a hydro-vacuum truck within the roadway to determine the location of the underground utilities and the ground conditions around the intersection for design purposes.

Timing Read more »

September 30 2016

Update: Shoring Work for Oakwood Station October 2016 - December 2016


Information as of September 29 2016 

 

What is the Crosstown? Read more »

September 29 2016

Subsurface Utility Engineering (SUE) Investigations Mount Pleasant Station

What Work is Taking Place?

  • To prepare for future construction of Mount Pleasant Station, crews will be conducting Subsurface Utility Engineering (SUE) investigations along Eglinton Avenue East and Mount Pleasant Road.
  • Crews will drill bore holes and use a hydro-vacuum truck within the roadway to determine the location of the underground utilities and the ground conditions around the intersection for design purposes. 
September 27 2016
September 21 2016

Monitoring Instrument Installation for Leaside (Bayview) Station

What Work is Taking Place?

  • As part of the preparatory works for the future Leaside Station construction, installation of above ground and in-ground monitoring points will take place in the vicinity of Eglinton Avenue East and Bayview Avenue. These monitors will provide information on ground conditions during station construction.

Timing Read more »