October 13 2017

Chaplin and Avenue Stations Open House

Thank you for attending the open house about Chaplin and Avenue Stations on October 12, 2017. 

For those of you who missed it, the presentation is here: Read more »

October 12 2017

Sewer Lining Activities at Avenue Station - Bypass Installation & Lining Operations

SEWER LINING AT AVENUE STATION

The entire sewer lining process will take approximately 4 – 6 weeks to complete.

Sewer bypass work takes place in the daytime construction hours.

Sewer lining work takes place on a 24 hour schedule.

WHAT WORK IS TAKING PLACE? Read more »

October 12 2017

Mount Dennis Station, Railway Corridor and Eglinton Maintenance and Storage Facility Open House

Thank you for attending the open house about Mount Dennis Station, Railway Corridor and Eglinton Maintenance and Storage Facility on October 11, 2017. 

For those of you who missed it, the presentation is here: Read more »

October 12 2017
October 12 2017

Laird - Leaside Construction Liaison Committee Meeting

The construction liaison committee meeting of Leaside and Laird Stations was held on October 11, 2017. You can see the presentation here: Read more »

October 12 2017

Early Morning Equipment Move and Deliveries at Chaplin Station

What Work is Taking Place?

On Friday October 13, crews will move heavy equipment from the southwest work zone eastward along Eglinton Avenue to the southeast work zone.

On Tuesday October 17, crews will receive a large delivery of steel beams to be hoisted from Eglinton Avenue into the work zone.  Read more »

October 11 2017

Overnight Work in the South Parking Lot at Kennedy Station

What Work is Taking Place?

As part of the ongoing work to construct Kennedy Station, crews will install temporary light poles and lines in the South Parking Lot starting as early as October 11, 2017. The work will be performed overnight in an effort to minimize disruption to the public and transit users.

Hours of Work Read more »

October 11 2017

Eglinton - Mount Pleasant Construction Liaison Committee Meeting

The construction liaison committee meeting of Eglinton and Mount Pleasant Stations was held on October 10, 2017. You can see the presentation here:

Read more »

October 10 2017

Mining at Avenue Station

Mining is expected to begin in November 2017, and will carry on through to late 2019.

What Work is Happening?

The Eglinton Crosstown includes a 10-kilometre underground portion, between Weston Road and Laird Drive, where 15 below-grade stations are under construction. Eleven will be built using a “cut-and cover” method and four, including Avenue Station, are going to be “mined.” 

Excavation of the entrances at Avenue Station is nearing completion and mining will begin soon. Read more »