August 28 2017

Traffic and Pedestrian Changes at Chaplin Station for Support of Excavation

What Work is Taking Place?

In winter 2017, crews began support of excavation work (shoring) of the station box at the future Chaplin Station, starting on the south side Eglinton Avenue West.  As early as Wednesday August 30, crews will implement the next stage of shoring for Chaplin Station.  

Please carefully review the map – traffic on Chaplin Crescent will be shifted to the west and changes to pedestrian crosswalks will be in effect.   Read more »

August 25 2017

Cedarvale Station: Road Closures for Utility Relocation & Support of Excavation

Updated: August 25, 2017
Original Issue Date: June 28, 2017

What Work is Taking Place?

The Cedarvale Station work zones are now in full swing as crews complete tunnel concrete pours, utility relocation, and support of excavation activities.

To continue to relocate and upgrade storm and sanitary sewer infrastructure and complete support of excavation, traffic changes in the vicinity of Cedarvale Station are required.

Throughout the Summer 2017, the following roads were closed at Eglinton Avenue West: Read more »

August 25 2017
August 24 2017

Fairbank Station Public Information Session

Thank you for attending the public information session about design plans of the parkette for the new Fairbank Station on August 23, 2017. 

For those of you who missed it, the presentation is here: Read more »

August 21 2017

Trailer Move at Caledonia Station

What work is taking place?

On August 22 and 23, crews will relocate a trailer at the Caledonia Station site to continue deep excavation.  Short-term lane reductions will be in effect.  Pedestrian access will be maintained.

Timing Read more »

August 18 2017

Update: Tunnel Concrete Pour for Laird Station

To progress construction at Laird Station and prepare for upcoming mining works, crews will be drilling from the right of way surface into the completed TBM tunnel to fill portions of the tunnels with concrete.

Hours of Work  Read more »

August 11 2017

Toronto Hydro-Electric System Limited (THESL) Relocation Work at Kennedy Station

What Work is Taking Place?
Crews will relocate and upgrade existing overhead hydro utilities between the West Service Roads to the East Service Roads of Eglinton Ave East in preparation for construction of the Kennedy Portal and the Kennedy LRT Station.