July 12 2017

Eglinton - Mount Pleasant Construction Liaison Committee Meeting

The construction liaison committee meeting of Eglinton and Mount Pleasant Stations was held on July 11, 2017. You can see the presentation here:

Read more »

July 12 2017

Upcoming: Shoring and Excavation at Oakwood Station

 

Since 2016, shoring and excavation work has been underway at the main and secondary entrance sites for the future Oakwood Station. Excavation at the Main entrance is currently underway and will be followed by mining operations in late 2017.  Read more »

July 10 2017

Water Main Investigations at Leaside Station

What Work is Taking Place

Crews will expose the portions of a water main on the north east corner of the Bayview Avenue and Eglinton Avenue East intersection. 

Timing  Read more »

July 06 2017

Chaplin - Avenue Construction Liaison Committee Meeting

The construction liaison committee meeting of Chaplin and Avenue Stations was held on July 5, 2017. You can see the presentation here:

July 04 2017

Overnight Preparatory Works for Sewer Re-lining at Laird Station

What Work is Taking Place

Sewer re-lining is a process intended to increase the durability of the sewers.  At Laird Drive and Eglinton Avenue East, local sewers will be re-lined in the vicinity of the construction sites.  Read more »

June 30 2017

Crane Installation at Laird Station Main Entrance

A large tower crane will be delivered and installed at the Laird Main Entrance during the week of July 3rd. 

What to Expect  Read more »

June 30 2017

Mount Dennis Railway Corridor Work - July 4 to July 30, 2017

What Work is Taking Place?

Crews are working in the rail corridor, within the vicinity of the Eglinton Avenue Bridge, preparing for the relocation of the CP Mainline Track. This work involves grading the track bed in the area where the tracks will be realigned, track bed leveling and shifting of the CP Diversion track to the correct alignment and cutting over-/shifting of the existing track.

Hours of Work Read more »

June 30 2017

Update: Dewatering System at Laird Station

Original issue dates: April 20, 2017 and June 7, 2017 Re-Issue date: June 30, 2017

The term “dewatering” means pumping from the ground water at a site where there will be excavation.  At Eglinton Avenue East and Laird Drive, dozens of small wells will be drilled along the curbside eastbound lane. Wells will be drilled and shallow trenches will be required to lay the pipes, pumps, wells and valves to do the work.   Read more »

June 29 2017

Cedarvale - Forest Hill Construction Liaison Committee Meeting

The construction liaison committee meeting of Cedarvale and Forest Hill stations was held on June 28, 2017. You can see the presentation here: