June 28 2019

Lane Closures at Fairbank Station - July 2, 2019

What Work is Taking Place?

As early as Tuesday July 2nd, crews will be reducing Eglinton Ave W from Northcliffe Blvd to Dufferin St to one lane from 7am – 11pm. The south lane will be closed for approximately 7 hours, followed by the north lane. Dufferin Street and Eglinton Avenue West will remain open while this work takes place.

Hours of Work Read more »

June 28 2019
June 27 2019

Concrete Pour at Mount Pleasant Station Friday June 28, 2019

 

On Friday June 28, 2019, crews will perform a concrete pour in the southwest work zone at Mt Pleasant Road and Eglinton Avenue.  The concrete will form part of the roof of Mount Pleasant Station.  A concrete pump will be set up within the work zone, and concrete trucks will stage on the west side of Mt Pleasant Road, north and south of Eglinton while this work takes place.  To ensure the integrity and continuity of the pour, work will begin early at 4:00 a.m. Read more »

June 27 2019

GUIDEWAY CONSTRUCTION AT THE EAST DON RIVER BRIDGE

GUIDEWAY CONSTRUCTION AT THE EAST DON RIVER BRIDGE

WHAT WORK IS TAKING PLACE? Read more »

June 27 2019

Construction Update at the Wilson Brook Culvert

Construction Update at the Wilson Brook Culvert

WHAT WORK IS TAKING PLACE? Read more »

June 25 2019

Updated: Duct Bank Installation at Warden Avenue for Traction Power Substation (TPSS) 11

Originally Posted: April 12, 2019 

Updated: June 25, 2019 

What Work is Taking Place? Read more »

June 24 2019

Short-term Pedestrian Rerouting for Sidewalk Repairs at Cedarvale Station

What Work is Taking Place?

On Wednesday June 26, 2019, pedestrian rerouting will be in effect while sidewalk repair work takes place.  The sidewalk on the north side of Eglinton Avenue West between Allen Road South and Park Hill Road will be closed, and pedestrians will be rerouted around the work zone. The sidewalk will reopen once the repairs are complete. 

Hours of Work  Read more »

June 24 2019

Temporary Lane Reductions Bayview

WHAT WORK IS TAKING PLACE?

Between June 25 and 28, crews will be repairing existing deck mats in the intersection of Bayview Avenue and Eglinton Avenue. Temporary lane reductions on Eglinton Avenue East immediately east and west of Bayview will occur during the works.

 

TIMING Read more »

June 19 2019

Crane Replacement Laird Main Entrance

The large tower crane currently in place at the Laird Main Entrance will be removed and replaced with a new crane. This work will take place for approximately 5 days between June 24th, 2019 and June 28th, 2019.

  Read more »