January 31 2019

Updated: Hydro Utility Relocation between Birchmount Road to Kennedy Road

What Work is Taking Place?

In support of construction of the future Crosstown Light Rail Transit, crews will continue relocation and upgrading of existing overhead and underground utilities between Birchmount Road and Kennedy Road. Work began in June of 2017 and will continue for another six (6) months. Read more »

January 28 2019

CROSS PASSAGE 10 CONSTRUCTION WORKS

Starting as soon as February 4th, an assessment of the existing dewatering system will take place at the Cross Passage site between Lillian Street and Redpath Avenue. Assessment works will take approximately five (5) days. Following the assessment the dewatering system will be recommissioned and will operate on a 24 hour basis. Periodic maintenance will be required.

 

TRAFFIC, TTC AND PEDESTRIAN IMPACTS Read more »

January 25 2019

Overnight Storm Sewer Connection Work at Brownlow Ave January 2019

What Work is Taking Place?

On January 30, crews will return to Brownlow Ave and Eglinton Ave to connect to the new storm sewer system installed last year.  Concrete will be removed so that crews can access the manhole below ground.  From there, concrete chipping and reforming will take place allowing the crews to connect to the new storm sewer infrastructure.  This work will be performed 24 hours per day.

Hours of Work Read more »

January 24 2019
January 24 2019

MONITORING INSTRUMENT INSTALLATION OAKWOOD STATION

 

WHAT WORK IS TAKING PLACE

Crews are required to replace two monitoring instruments in the Oakwood Avenue and Eglinton Avenue West intersection.

  Read more »

January 22 2019

Updated: Resumption of Overnight Wet Utilities Work at Forest Hill Station January 24, 2019

What Work is Taking Place?

Crews have been completing overnight wet utility and hydro utility installation work at Forest Hill Station since September 2018; this work will continue through until mid-February 2019. 95% of all utilities relocation and installation work at Forest Hill Station have been completed.

Resuming January 24, 2019, overnight water main chamber construction will commence on Eglinton Avenue, east of Bathurst Street. Traffic in the vicinity of the work area will be reduced to one (1) lane only, alternating in each direction.  Read more »

January 22 2019

Overnight Closure of Temporary Access Road for Utility Work

Last Updated: January 25, 2019

WHAT WORK IS TAKING PLACE?

To facilitate the ongoing utility relocation at the future Kennedy Station, there will be overnight closures of the Temporary Access Road.

Work began on Tuesday, January 22, 2019 and was scheduled for approximately three (3) nights. Due to extreme cold temperatures the work was incomplete. Crews will resume sleeving out wires on the hydro lines at the temporary access road on Tuesday, January 29, 2019. Read more »

January 22 2019

Reopening of North End of Existing East Platform at Kennedy GO Station

What Work is Taking Place?

Kennedy Station is an interchange station with connections to the GO Transit Stouffville Line, the TTC Scarborough RT, the TTC Bloor-Danforth subway, and a TTC bus terminal. Construction of the Eglinton Crosstown LRT Kennedy Station will include upgrades to the existing Kennedy Station infrastructure. Read more »

January 22 2019

Traffic Deck Replacement at Eglinton West Subway Station (Cedarvale)

What Work is Taking Place?

  • Crews will be replacing the road decking on the north side of Eglinton Avenue from Park Hill Road to Allen Road South.

Hours of Work Read more »