Ionview Road

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

Syndicate content
 
December 012020

North and South Platform Shelter Installation at Ionview Stop - December 8, 2020

 

     

 

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will install permanent shelters at the Ionview stop north and south platform. North platform installation will begin as early as December 8, 2020 for approximately four days and south platform installation will follow for approximately three days.  

 

What to Expect Read more »

October 292020

Overnight OCS Cable Works on Eglinton Ave between Birchmount Road and Ionview Road - November 4-5, 2020

 

 

 

What Work is Taking Place?

Crews will be installing OCS (Overhead Catenary System) cables along Eglinton Avenue East between Birchmount Road and Ionview Road. Overhead catenary is the system installed overtop of the rails of a light rail system, to provide operational power to the LRVs (Light Rail Vehicles).  Installation will take place overnight November 4-5, 2020 between the hours of 9:00 p.m. and 6:00 a.m.

  Read more »

October 222020

Closure on Rosemount Drive North of Eglinton Avenue East - Extended to late December 2020

 

 

What Work is Taking Place?

As part of the ongoing works to replace the existing culvert at Massey Creek, the current traffic configuration at Rosemount Drive and Eglinton Avenue East will be extended to late December 2020. Rosemount Drive will remain closed north of Eglinton Avenue East and north-south through-traffic will be prohibited for the duration of the work.

 

What to Expect Read more »

October 052020

UPDATED: THESL Pole Relocation - Eglinton Avenue East between Ionview and Kennedy Road - October 6, 2020

 

Original Post: Aug 13, 2020

Updated on October 5, 2020

 

Crews will be relocating Toronto Hydro-Electric System (THESL) poles to their permanent positions along Eglinton Avenue East between Ionview Road and Kennedy Road. Work will be completed in sections and is expected to begin October 6 through to early November 2020. All works are in support of the construction of the Crosstown LRT tracks and guideway (dedicated transit lane) in the centre of Eglinton Avenue East.

  Read more »

September 302020

Pharmacy to Kennedy Construction Liaison Committee Meeting - September 2020

Construction Liaison Committee of Pharmacy to Kennedy was held on September 29, 2020. You can see the presentation here:

 


Read more »

September 302020

Overnight Track Works on Eglinton Ave East between Birchmount and Kennedy Road - October 5-9, 2020

 

 

What Work is Taking Place?

Crews will be installing and performing welding activities on the LRT tracks within the guideway work zone on Eglinton Avenue East between Birchmount Road and Kennedy Road. Work will take place October 5-9, 2020 between the hours of 5:00 p.m. and 3:30 a.m.

 

What to Expect Read more »

August 262020

Boulevard Restoration Works Eglinton Ave East North Side, Ionview Road to Kennedy Road - Extended to Late September

 

Original Post: July 28, 2020

Last Update: August 26, 2020

 

What Work is Taking Place?

Crews will continue boulevard restoration works on the north side of Eglinton Avenue East between Ionview and Kennedy Road. Partial or full driveway closures will be required to perform grading works to align driveways with the new road surface on Eglinton Avenue East.  Driveways may be restricted partially or fully beginning July 6, 2020. This work has been extended through to late September 2020.  Read more »