Keele Street

Looking for updates near a specific intersection?

Choose an intersection from the drop down list to view all of the latest news and construction updates in that area. Intersections are listed from west to east with Eglinton as the main cross-street.




Syndicate content
 
December 152016

Keelesdale Station Traffic Reconfiguration - Thursday December 22, 2016 (overnight)

What Work is Taking Place?

As part of the continued traffic staging set up at Keele Street/Trethewey Drive and Eglinton Avenue West for support of excavation works for the Keelesdale Station traffic restrictions in this area is changing. Read more »

September 062016

Pedestrian Safety near Construction Sites

Construction of the Eglinton Crosstown LRT line, including 15 underground stations, is underway. Since the end of school, many construction sites have been set up for station construction and the set-up of some major intersections along Eglinton Avenue has been changed.

Pedestrian Information Read more »

May 112016

Overnight Watermain work for Keelesdale Station

Since December 2015, crews have been conducting work along Eglinton Avenue West in the vicinity of the future Keelesdale Station to prepare for the next phase of construction of the Eglinton Crosstown. Read more »

May 052016

Keelesdale Station Open House

Thank you for attending our Keelesdale station open house on May 4, 2016. 

For those of you who missed it, the presentation is here:

Read more »

April 072016

Tunnelling: What you may experience

As you may know, the Eglinton Crosstown includes a 10-kilometre underground portion, between Keele Street and Laird Drive. For the tunnelled portion, locomotives run along interim track and transport materials and haul spoils in and out of the tunnels to the extraction shafts. Tunnel boring machines (TBMs) and muck removal operations run around the clock - 24 hours a day. Read more »

February 012016

Tunnelling: What you may experience

Dear Neighbour:

As you may know, the Eglinton Crosstown includes a 10-kilometre underground portion, between Keele Street and Laird Drive.For the tunnelled portion, we have tunnel boring machines (TBMs) operating around the clock - 24 hours a day, seven days week.

On average, the tunnel boring machines each travel approximately 10-15 metres per day. TBMs are working approximately 16-20 metres below ground, but we sometimes hear from nearby residents who may experience noise and vibration from the TBMs as they pass through the area. Read more »

January 282016

Continuing Preparatory Works for the Future Keelesdale Station

Since December 2015, crews have been conducting preparatory activities along Eglinton Avenue West in the vicinity of the future Keelesdale (formerly Keele) Station to prepare for the next phase of construction of the Eglinton Crosstown. Work will continue through winter 2015/2016 in advance of the construction of the Keelesdale Station, which will begin in spring 2016.

What work is starting and where? 

Read more »