September 032014

Open houses in September

Metrolinx is hosting three open houses in September at various locations along the Eglinton corridor to provide an update on current Crosstown construction.

Join us at one of the following sessions to hear what is happening, why it needs to happen and how it may impact you:

Tuesday, September 9, 2014

7:00 - 9:00 pm Read more »

August 212014

What phase of work is starting in the vicinity of Sutherland Drive?

What phase of work is starting in the vicinity of Sutherland Drive? Read more »

August 152014

Overnight Lane Reduction to a Single Lane between Brentcliffe Road and Leslie Street Starting August 17, 2014, 10:00 p.m.

What/Where: Crews will be working on advanced utility construction and relocation between Brentcliffe Road and Leslie Street.  Read more »

August 072014

Overnight Lane Reduction to a Single Lane between Brentcliffe Road and Leslie Street, Starting late August 2014

What/Where: Crews will be working on advanced utility construction and relocation between Brentcliffe Road and Leslie Street. Read more »

July 032014

Laird Station East Headwall Construction for Twin Tunnels Stages One & Two – Reminder

The Eglinton Crosstown is a 19-kilometre light rail transit line that will run along Eglinton Avenue through the heart of Toronto, with an underground central section. The line will connect Mount Dennis in the west to Kennedy Road in the east, and the new service will be up to 60% faster than the bus service today. Read more »

July 022014

Rolling Lane Closures on Sutherland Drive at Eglinton Avenue East - Week of June 23, 2014

The Eglinton Crosstown is a 19 kilometre light rail transit (LRT) line that will run along Eglinton Avenue through the heart of Toronto, with an underground central section. The line will connect Mount Dennis in the west to Kennedy Road in the east, and the new service will be up to 60% faster than the bus service today.

What work is starting?

What: Crews will be installing ground movement monitoring equipment.   Read more »