Lane Reduction for U-Fill Pour at Caledonia Station July 16, 2020

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

 
July 15, 2020

What Work is Taking Place?

On Thursday July 16, crews at Caledonia will be pouring u-fill into the station box. During the pour, westbound Eglinton Ave W will be reduced to one (1) lane only between Blackthorne Ave and Gabian Way. Lane reductions will begin as early as 5:00am and last for approximately ten hours.

Hours of Work

  • Thursday July 16, 2020
  • Lane reductions will begin at approximately 5:00am and last for approximately ten hours.
  • The contractor may not always work during permitted hours but may do so at its discretion.
  • Work may be rescheduled due to weather conditions or unforeseen circumstances.
  • This work may be longer or shorter than expected.

Work Area Map

 

What to Expect

  • Concrete trucks will be entering and exiting the workzone.
  • Motorists can expect delays when travelling through the intersection.
  • One westbound lane on Eglinton Ave may be occupied between Blackthorne Ave and Gabian Way while this work takes place.
  • There will be no impacts to pedestrian routes or TTC stops.

 

Travelling Smart during Construction

Travel delays are expected with the Crosstown construction. Please allow extra time for your journey. Traffic will be extra heavy at peak periods during the Crosstown construction. When possible, please travel during the off-peak period between 10 a.m. and 3 p.m.

Stay Informed

Sign up for e-mail updates at www.thecrosstown.ca/sign-up or download the Crosstown traffic app to get real-time traffic and transit information for the Eglinton corridor.

Disponible en français.