Lane Reduction on Transway Crescent at Kennedy Station May 17-21,2021
Looking for information related to a specific area?
Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).
- Allen Road
- Avenue Road
- Bathurst Street
- Bayview Avenue
- Bermondsey Road
- Birchmount Road
- Black Creek Drive
- Brentcliffe Road
- Caledonia Road
- Chaplin Crescent
- Don Mills Road
- Donlea Drive/Hanna Road
- Don Valley Parkway (DVP)
- Dufferin Street
- Ferrand Drive
- Ionview Road
- Keele Street
- Kennedy Road
- Laird Drive
- Leslie Street
- Lebovic Avenue
- Little Blvd.
- Mount Pleasant Road
- Oakwood Avenue
- Petman Avenue
- Pharmacy Avenue
- Victoria Park Avenue
- Warden Avenue
- Weston Road
- Wynford Drive
- Yonge Street
May 17 - May21, 2021
What Work Is Taking Place?
As early as Monday, May 17 and lasting until Friday, May 21, part of Transway Crescent will be reduced to one lane to accommodate the installation of a new sewer management system. Crews will be installing a new manhole on Transway Crescent and connecting a sewer pipe to the Main Entrance compound. Work in the roadway will occur between 7:00 am and 5:00 pm, and the road will be re-opened each evening. Flaggers will be present to direct cars and buses through the roadway.
What to Expect
Flaggers will be present to direct cars and buses through the reduced lane. Pedestrians travelling on the north sidewalk will be directed around the work zone. Minor noise impacts can be expected.
HOURS OF WORK
- Work will take place as early as Monday, May 17 until Friday, May 21
- Road work will take place daily from 7:00 am and 5:00 pm
- Work may be rescheduled due to weather conditions or unforeseen circumstances
- The contractor may not always work during the permitted hours but may do so at its discretion
- This work may take longer or shorter than expected
TRAFFIC DETAILS
- Transway Crescent will be reduced to one lane daily from 7:00 am and 5:00 pm, and will re-open each night
PEDESTRIAN DETAILS
- Pedestrians travelling on the north sidewalk will be directed around the work zone
OTHER INFORMATION
- Minor noise impacts can be expected.