Laneway Closure for Overnight Concrete Pour at Forest Hill Station - October 30, 2019

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

 
October 28, 2019

On Wednesday October 30, 2019 beginning at 4:00 a.m. crews will close the Hilltop Road-Bathurst Street laneway behind the Forest Hill Station Secondary Entrance to conduct a concrete pour. The concrete will form the exterior wall of the Secondary Entrance. The pour is one of a series of concrete pours that will take place in 2019 to construct the Secondary Entrance. The pedestrian walkway around the Secondary Entrance site will be closed while the pour takes place. Once the pour is complete, the pedestrian walkway around the Secondary Entrance site will re-open.

Details

  • Wednesday October 30, 2019 at 4:00 a.m. for approximately eight (8) hours
  • In the event of inclement weather-dependent, this work will take on Thursday October 31, 2019

Construction Configuration

Laneway Closure for Overnight Concrete Pour at Forest Hill Station Wednesday October 30, changes to pedestrian routing

What to Expect

  • The Hilltop Rd-Bathurst St laneway will be closed behind the Secondary Entrance site
  • The pedestrian walkway around the Secondary Entrance site will be temporarily closed during this activity
  • Overnight noise from construction as well as site lighting can be expected
  • Property access, including access to parking spaces in the laneway, will be maintained
  • Motorists can expect delays when accessing the laneway
  • 10+ concrete trucks expected per hour during the concrete pour

Pedestrian Details

  • The sidewalk on the north side of Eglinton Ave W will remain closed at Secondary Entrance
  • The pedestrian walkway around the Secondary Entrance site will be temporarily closed during this activity
  • Pedestrians can cross Eglinton at Rostrevor Rd to the west and Bathurst St to the east

 Traffic Details

  • No through access in the Hilltop Rd-Bathurst St laneway will be permitted
  • Bathurst St and Eglinton Ave W will remain open during this work
  • Peveril Hill Rd N will remain closed at Eglinton during this work Eglinton Ave
  • The sidewalk on the north side of Eglinton Ave W will remain closed at Secondary Entrance

 