UPDATED: Mid-block Guideway and Stop Construction from Victoria Park Avenue to Ionview Road
Looking for information related to a specific area?
Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).
- Allen Road
- Avenue Road
- Bathurst Street
- Bayview Avenue
- Bermondsey Road
- Birchmount Road
- Black Creek Drive
- Brentcliffe Road
- Caledonia Road
- Chaplin Crescent
- Don Mills Road
- Donlea Drive/Hanna Road
- Don Valley Parkway (DVP)
- Dufferin Street
- Ferrand Drive
- Ionview Road
- Keele Street
- Kennedy Road
- Laird Drive
- Leslie Street
- Lebovic Avenue
- Little Blvd.
- Mount Pleasant Road
- Oakwood Avenue
- Petman Avenue
- Pharmacy Avenue
- Victoria Park Avenue
- Warden Avenue
- Weston Road
- Wynford Drive
- Yonge Street
Original Post: November 15, 2019
Updated: January 6, 2020
What Work is Taking Place
As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be conducting mid-block guideway and stop construction between Victoria Park Avenue and Ionview Road, for approximately eight (8) months through spring 2020.
Guideway and stop construction includes: cutting and removal of asphalt, excavation, installation of subgrade materials, duct banks installation, track drainage, track installation, signal work and stop construction.
The sequence of stop construction will begin with Pharmacy, Hakimi, O’Connor (at Victoria Park Avenue), Birchmount, Ionview, and Golden Mile (at Warden Avenue) consecutively.
Hours of Work
• Construction will take place between 7:00 a.m. and 11:00 p.m.
• The contractor may not always work during the permitted hours but may do so at its discretion.
• Work may be rescheduled due to weather conditions or unforeseen circumstances.
What to Expect
• Daily temporary lane closures.
• Periodic sidewalk and crosswalk closures.
• Noise from construction equipment, generators and vehicles.
• Nearby businesses and residents can expect noise from excavation, bobcats, trucks and other construction equipment as well as site lighting.
Traffic and Pedestrian Impacts
• A minimum of one lane of eastbound and westbound through traffic will be maintained during this work.
• Intermittent closures of the east and west crosswalks will be in effect during this work; one north-south crosswalk will remain open at all times.
• Emergency services access will be maintained.
TTC Impacts
• TTC bus stops in the affected area may be relocated for the safety of transit riders.
• Relocation and re-routing of bus stops and buses is done in consultation with TTC to ensure construction can continue safely, while minimizing impact on the community and customers.
Stay Informed
• Sign up for e-mail updates at http://www.thecrosstown.ca/sign-up or download the aCrosstown traffic app to get real-time traffic and transit information for the Eglinton corridor.