July 18 2018

Update: Facility Services Building Construction at Eglinton Station

What Work is Taking Place?

Beginning July 6th, 2018, work will get underway building the foundation and housing for the Facility Services Building for the TTC Line 1 Subway system. Crews will also undertake various activities inside the TTC station. Read more »

July 18 2018

Construction Notice - Overnight Wet Utilities Work at Mount Pleasant Station onThursday July 19

 

Overnight Wet Utilities Work at Mount Pleasant Station

What Work is Taking Place? Read more »

Categories:
July 17 2018

Construction Notice - Tentative Overnight Work at Mount Pleasant Station - July 19, 2018

Planned Overnight Work at Mount Pleasant Station

Thursday July 19, 2018*

 

 What Work is Taking Place?

On Thursday July 19, 2018 from 8:00 p.m. overnight to Friday morning at 6:00 a.m. Eglinton Avenue will be reduced to one shared lane of traffic between Mt. Pleasant Road westward toward Brownlow Avenue Read more »

July 13 2018

Construction Notice: Support of Excavation at Mount Pleasant Station

 

Support of Excavation at Mount Pleasant Station  

 

What Work is Taking Place? Read more »

July 12 2018

Leaside - Laird Construction Liaison Committee Meeting

The construction liaison committee meeting of Leaside and Laird Stations was held on July 11, 2018. You can see the presentation here:

Read more »

July 12 2018

Update: Resumption of Overnight Utility Relocation Work on Transway Crescent for the Future Kennedy Station

What Work is Taking Place?

As part of construction of the future Kennedy Station, crews will resume relocating watermain and sanitary utilities on Transway Crescent, starting as soon as July 15, 2018.

To reduce impacts to the community and commuters this work will be performed overnight and will take approximately three (3) weeks to complete.  The work is part of the larger upgrade and relocation of utilities for the Eglinton Crosstown LRT.

Stage 3 Read more »

July 11 2018

Eglinton & Mount Pleasant Construction Liaison Committee Meeting

The construction liaison committee meeting of Eglinton and Mount Pleasant Stations was held on July 10, 2018. You can see the presentation here:

Download the presentation

July 10 2018
July 09 2018

OVERNIGHT WATER MAIN TESTING LAIRD STATION

OVERNIGHT WATER MAIN TESTING

LAIRD STATION

On Wednesday, July 11, crews will test local watermains along Eglinton Avenue East from Brentcliffe Drive to Sutherland Drive. Periodic testing of utilities during the mining operations ensures work continues safely.

TIMING  Read more »