What Work is Taking Place?

Since April 14, crews have carried out weekend closures of Mt. Pleasant Road between Eglinton Ave E and Roehampton Ave to perform hydro utility relocation work.

To minimize the impact to road users and the number of closures required, this work will be performed overnight.  The road closure will be in place the duration of the weekend.  Through traffic on Eglinton Ave E will be maintained. 

Due to a planned event on Sunday May 6, TTC buses will be detoured onto local streets via Mt. Pleasant Road.  Increased TTC traffic in the vicinity of Roehampton Avenue and Redpath Avenue can be expected between 5:00 a.m. and 12:00 noon.

Upcoming Construction Staging

Hours of Work

  • Mt Pleasant Road will be closed from Friday May 4 at 9:00 p.m. until Monday May 7 at 5:00 a.m.
  • Work will be carried out on a 24-hour basis for the duration of the closure.
  • Work may be rescheduled due to unforeseen circumstances or inclement weather

What to Expect

  • Mt Pleasant Rd will be closed between Roehampton Ave and Eglinton Ave E
  • TTC bus traffic on local streets can be expected on Sunday May 6, 2018
  • Vehicle traffic will be rerouted around the closure
  • Pedestrian and local property access will be maintained
  • Flag persons will be present to assist with traffic control

Traffic Details

  • Local access will be maintained from Roehampton Ave only.
  • Traffic lanes on Mt Pleasant Rd will be rerouted around the closure
  • Eglinton Ave E will remain open