New Traffic Configuration at Rosemount Drive and Eglinton Avenue East - January 2, 2020
Looking for information related to a specific area?
Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).
- Allen Road
- Avenue Road
- Bathurst Street
- Bayview Avenue
- Bermondsey Road
- Birchmount Road
- Black Creek Drive
- Brentcliffe Road
- Caledonia Road
- Chaplin Crescent
- Don Mills Road
- Donlea Drive/Hanna Road
- Don Valley Parkway (DVP)
- Dufferin Street
- Ferrand Drive
- Ionview Road
- Keele Street
- Kennedy Road
- Laird Drive
- Leslie Street
- Lebovic Avenue
- Little Blvd.
- Mount Pleasant Road
- Oakwood Avenue
- Petman Avenue
- Pharmacy Avenue
- Victoria Park Avenue
- Warden Avenue
- Weston Road
- Wynford Drive
- Yonge Street
What Work is Taking Place
As part of the ongoing works to replace the existing culvert at Massey Creek, a new traffic configuration will be implemented at Rosemount Drive and Eglinton Avenue East as early as Thursday January 2, 2020. Rosemount Drive will be closed north of Eglinton Avenue East and north-south through traffic will be prohibited for the duration of the work.
Work includes excavation, concrete works, shoring installation and backfilling.
The new traffic configuration will be implemented as early as January 2, 2020 and will last for two (2) months.
Note: Upon the completion of guideway work at the intersection, Rosemount Drive north of Eglinton Avenue East will be opened as early as December 21, 2019 through January 2, 2020.
Upcoming Traffic Configuration
Hours of Work
• The new traffic configuration will be implemented as early as January 2, 2020 and will last for two (2) months.
• Work will be performed between the hours of 7:00 a.m. and 11:00 p.m.
• Work may be rescheduled due to weather conditions or unforeseen circumstances
Traffic and Pedestrian Impacts
• Rosemount Drive north of Eglinton Avenue East will be closed
• Wesbound right turns onto Rosemount Drive will be prohibited.
• Southbound traffic on Rosemount Drive will be diverted north of Eglinton Avenue East
• Both westbound and eastbound left turns onto Rosemount Drive will be prohibited
• The northwest corner of Rosemount Drive and Eglinton Ave East will remain closed, pedestrians will be rerouted to the south sidewalk.
• A minimum of one lane of eastbound and westbound through traffic will be maintained during this work
• Emergency services access will be maintained
TTC Impacts
• All temporary TTC bus stops will remain in their current locations.
• Relocation and re-routing of bus stops and buses is done in consultation with TTC to ensure construction can continue safely, while minimizing impact on the community and customers
Stay Informed
• Sign up for e-mail updates at http://www.thecrosstown.ca/sign-up or download the aCrosstown traffic app to get real-time traffic and transit information for the Eglinton corridor.