OVERNIGHT CONCRETE POUR AT CALEDONIA STATION DECEMBER 8, 2018

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

 
December 3, 2018

 

What Work is Taking Place?

On Saturday December 8, crews will perform an overnight concrete pour at Caledonia Station. A concrete pump will be on site and concrete trucks will queue at the centre lane on Eglinton Ave W, east of Blackthorne Ave. 

To ensure the quality of the pour and minimize the impact to TTC and road users, this activity will be performed overnight.   

Hours of Work 

  • Saturday, December 8, 2018 from 1:30am (overnight) to 10:00am
  • In the event of inclement weather, this work will be rescheduled for another date


Construction Staging

workzone Caledonia pour dec 8

What to Expect

 

  • Overnight noise from concrete trucks, equipment and site lighting can be expected. 
  • Trucks will be staged in the centre lane on Eglinton Ave W. 
  • Motorists can expect delays when travelling through the intersection. 
  • One westbound lane on Eglinton Ave may be occupied while this work takes place.

 

 For more information, please contact Lancefield Morgan at the West Community Office.

Thank you for your continued patience as we work to build this important project.

Please support your local businesses during construction.

Sign up at www.thecrosstown.ca/sign-up to receive regular email updates.