Overnight Sanitary Pipe Installation between Ionview Road and Kennedy Road
Looking for information related to a specific area?
Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).
- Allen Road
- Avenue Road
- Bathurst Street
- Bayview Avenue
- Bermondsey Road
- Birchmount Road
- Black Creek Drive
- Brentcliffe Road
- Caledonia Road
- Chaplin Crescent
- Don Mills Road
- Donlea Drive/Hanna Road
- Don Valley Parkway (DVP)
- Dufferin Street
- Ferrand Drive
- Ionview Road
- Keele Street
- Kennedy Road
- Laird Drive
- Leslie Street
- Lebovic Avenue
- Little Blvd.
- Mount Pleasant Road
- Oakwood Avenue
- Petman Avenue
- Pharmacy Avenue
- Victoria Park Avenue
- Warden Avenue
- Weston Road
- Wynford Drive
- Yonge Street
What Work is Taking Place?
In support of the construction of the future Kennedy Station, crews will be conducting sanitary pipe installation activities in the center of Eglinton Avenue East, between Ionview Road and Kennedy Road. This work is expected to begin as early as March 6, 2019 and lasting for approximately one (1) week.
In an effort to minimise disruption and to protect the safety of the local community and commuters, work will be performed overnight.
Stage 1
Stage 2
Stage 3
Hours of Work
- Date: as early as March 6, 2019 for approximately one (1) week.
- Time: Between 9:00 pm and approximately 7:00 am
- Note: Unexpected circumstances (weather, equipment failure, etc.) may also change the above interruption plans or prolong the interruption. If this occurs, we will endeavour to provide reasonable notice.
What to Expect
- Installation of a six (6) feet discharge pipe in the center of Eglinton Avenue East — east of Ionview Road.
- Nearby residents and businesses can expect noise in the area caused by trucks and other construction equipment, as well as dust from drilling activity and debris removal.
- Work will be completed in stages during this work.
- Driveway access maybe restricted during this work.
- There will be noise and vibration associated with these activities.
Traffic and Pedestrian Impacts
- Lane reductions and turn restrictions will be required to safely perform this work.
- Paid-Duty Police Officers will be present to direct traffic during this work.
- A minimum of one (1) lane of traffic will be maintained at all times.
- All open sidewalks and crosswalks will be maintained during this work. Please watch for signs directing pedestrians to alternate routes.
- As always, please take care when travelling near work sites.
TTC Impacts
- Relocations and re-routing of bus stops is done in consultation with TTC to ensure construction can continue safely while minimizing the impact on the community and customers.
Stay Informed
Sign up for e-mail updates at http://www.thecrosstown.ca/sign-up or download the aCrosstown traffic app to get real-time traffic and transit information for the Eglinton corridor.
For more information, please contact Phil Rodriques at the East Community Office.
Thank you for your continued patience as we work to build this important project.
Please support your local businesses during construction.