What's New?
Looking for information related to a specific area?
Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).
- Allen Road
- Avenue Road
- Bathurst Street
- Bayview Avenue
- Bermondsey Road
- Birchmount Road
- Black Creek Drive
- Brentcliffe Road
- Caledonia Road
- Chaplin Crescent
- Don Mills Road
- Donlea Drive/Hanna Road
- Don Valley Parkway (DVP)
- Dufferin Street
- Ferrand Drive
- Ionview Road
- Keele Street
- Kennedy Road
- Laird Drive
- Leslie Street
- Lebovic Avenue
- Little Blvd.
- Mount Pleasant Road
- Oakwood Avenue
- Petman Avenue
- Pharmacy Avenue
- Victoria Park Avenue
- Warden Avenue
- Weston Road
- Wynford Drive
- Yonge Street
Upcoming Concrete Pour at Mount Pleasant Road and Eglinton Avenue East - Jan 30, 2021
As early as Saturday January 30, 2021 crews at Mount Pleasant Station will perform a major concrete pour within the work zones on the north side of Eglinton Avenue East, east of Mount Pleasant Road. The concrete will form one of the permanent station structures underground. To ensure the integrity and continuity of the pour, work will begin as early as 6:00 a.m. and take approximately 12 hours to complete.
Cedarvale & Forest Hill Construction Update - January 27, 2021
The following construction update for Cedarvale and Forest Hill stations has been updated as recently as January 27, 2021. You can view the presentation here:
Road Closure for Emergency Sewer Servicing at Hilltop Road - January 25, 2021
What Work is Taking Place?
On Monday January 25, 2021, Hilltop Road will be closed at Eglinton Avenue West while crews perform emergency servicing of a sewer bypass. Upon completion of the work, Hilltop Road will re-open.
What to Expect
Concrete Pour at Fairbank Station - January 22, 2021
What Work is Taking Place?
Crews at Fairbank Station continue to perform large concrete pours. Crews will be pouring on Friday January 22, beginning as early as 7:00 a.m. Concrete pumps will be placed within the Main Entrance work zone. Concrete trucks will be staged on Dufferin Street, south of Eglinton Avenue West. Dufferin Street and Eglinton Avenue West will remain open while this work takes place.
Overnight OCS Cable Installation on Eglinton Ave at Sinnott Road, Birchmount Road, Rosemount Drive
What Work is Taking Place?
Leaside and Laird CLC - January 11, 2021
Construction Updates for Leaside and Laird.