***POSTPONED *** Test Pits at Weston Road and Hollis Street - October 22 & 23, 2020

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

 
October 21, 2020

 

What Work is Taking Place?

Crews at the Rail Corridor continue west Rail Corridor development, including utility installations. On Tuesday, October 27 & Wednesday, October 28, crews will continue to do test pits on Weston Road and Hollis Street. All current traffic restrictions will remain in place.  

 

What to Expect

Crews will be using a vac truck for the test pits and noise can be expected. The working hours remain from 7:00am until 7:00pm, however the actual working duration is only four hours.  On site, crews will be using a roller to perform backfilling and compaction works and vibrations can be expected. On site, noise and vibration can be expected from the continued installation of the new storm pipe. 

 

HOURS OF WORK

  • Crews will be working from as early as 7:00am until 7:00pm
  • Work may be rescheduled due to weather conditions or unforeseen circumstances
  • The contractor may not always work during the permitted hours but may do so at its discretion
  • This work may take longer or shorter than expected

 

TRAFFIC IMPACTS

  • All current traffic restrictions will remain in place
  • Access to Weston Rd and Eglinton Ave W will be maintained

 

PEDESTRIAN IMPACTS

  • All current pedestrian restrictions will remain in place
  • Access to businesses and properties will be maintained