Pre-Cast Panel Installations at Avenue Station's Main Entrance - November 16, 2021
Looking for information related to a specific area?
Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).
Choose an intersection (A to Z)
- Allen Road
- Avenue Road
- Bathurst Street
- Bayview Avenue
- Bermondsey Road
- Birchmount Road
- Black Creek Drive
- Brentcliffe Road
- Caledonia Road
- Chaplin Crescent
- Don Mills Road
- Donlea Drive/Hanna Road
- Don Valley Parkway (DVP)
- Dufferin Street
- Ferrand Drive
- Ionview Road
- Keele Street
- Kennedy Road
- Laird Drive
- Leslie Street
- Lebovic Avenue
- Little Blvd.
- Mount Pleasant Road
- Oakwood Avenue
- Petman Avenue
- Pharmacy Avenue
- Victoria Park Avenue
- Warden Avenue
- Weston Road
- Wynford Drive
- Yonge Street
November 12, 2021
What Work is Taking Place?
As early as Tuesday November 16, 2021, crews at Avenue Station will begin installing pre-cast concrete panels on the exterior walls of the Main Entrance building. To safely carry out the works, westbound traffic on Eglinton Avenue West will be reduced to one lane at the Main Entrance. This work is expected to take place Monday – Saturday, between 2:00 p.m. – 10:00 p.m. for approximately two (2) weeks. The lane reduction will remain in place on a 24-hour basis while this work takes place.
What to Expect
Noise from construction activity, including material loading, can be expected. Expect delays while travelling through the intersection.
HOURS OF WORK
- As early as Tuesday November 16, 2021
- This work is expected to take place Monday – Saturday, between 2:00 p.m. – 10:00 p.m. for approximately two (2) weeks
- The lane reduction will remain in place on a 24-hour basis while this work takes place
- This work may be delayed or rescheduled due to inclement weather or unforeseen circumstances
TRAFFIC DETAILS
- Westbound traffic on Eglinton Avenue West will be reduced to one lane at the Main Entrance
PEDESTRIAN DETAILS
- No changes to the current pedestrian routes are expected as a result of this work
TRANSIT INFORMATION
- Access to TTC will be maintained at all times
- Please visit www.ttc.ca for more information
Disponible en français.
Sign up for e-mail updates at www.thecrosstown.ca/sign-up
Categories: