November 07 2017

Traffic Changes at Leaside Station

What Work is Taking Place?

Starting as soon as Thursday, November 9th, there will be a couple of changes to the existing traffic set up around Eglinton Avenue and Bayview Avenue:

Left turn restriction from Mann Avenue to westbound Eglinton Avenue East Read more »

November 06 2017

Installation of Temporary Traffic Signals Across Eglinton Avenue East Between Leslie Street and Kennedy Road

Updated: November 6, 2017

Original Post: October 20, 2017

What Work is Taking Place?

Crews will remove existing traffic signals and install temporary traffic signals on Eglinton Avenue East between Leslie Street and Kennedy Road, to make way for the construction of future surface stops for the Eglinton Crosstown LRT.

Timing Read more »

November 03 2017

Cedarvale and Forest Hill Stations Open House

Thank you for attending the open house about Cedarvale and Forest Hill Stations on November 2, 2017. 

For those of you who missed it, the presentation is here: Read more »

November 03 2017
November 03 2017

Brentcliffe - Victoria Park Construction Liaison Committee Meeting

The construction liaison committee meeting of Brentcliffe - Victoria Park was held on November 2, 2017. You can see the presentation here:

Read more »

November 03 2017

Sanitary Sewer Installation and Overnight Diversion Work at Chaplin Station

WHAT WORK IS TAKING PLACE?

Part of the work to be done within the north side work zone includes the installation of a new sanitary sewer system. The new sanitary sewer will run along Eglinton Avenue West between Chaplin Crescent and Latimer Avenue.  

To complete the installation of the new sewer, crews will need to divert the existing sanitary sewer system flow. Diversion work involves cutting into the existing sanitary sewer pipe and temporarily diverting the flow of sewage while the new pipes and property connections are installed. Read more »

November 03 2017

Utilities Works at Leaside Station

What Work is Taking Place?

On Monday November 6th, work will be completed to bring power to the secondary entrance area. A small work zone will be in place on the west side of Bayview Avenue near the driveway access to the Metro Parking.

Minor utility works occur periodically within the current construction zones with no additional traffic or pedestrian impacts. Read more »

November 03 2017

Update: Deep Excavation and Dewatering at Caledonia Station

What work is taking place?

Deep excavation and dewatering have been underway at Caledonia Station since spring 2017. Read more »

November 02 2017

Chaplin and Avenue Construction Liaison Committee Meeting

The construction liaison committee meeting of Chaplin and Avenue Stations was held on November 1, 2017. You can see the presentation here:

Read more »