January 09 2018

Overnight Preparatory Works for Sewer Lining at Oakwood Station

 

In advance of upcoming mining works at Oakwood Station, crews must install sewer linings to the existing sewer infrastructure on Eglinton Avenue West between Oakwood Avenue and Times Road. Work also includes one location on Times Road, just north of Eglinton Avenue.  Read more »

January 09 2018

Overnight Preparatory Works for Sewer Lining at Oakwood Station

 

In advance of upcoming mining works at Oakwood Station, crews must install sewer linings to the existing sewer infrastructure on Eglinton Avenue West between Oakwood Avenue and Times Road. Work also includes one location on Times Road, just north of Eglinton Avenue.  Read more »

January 08 2018
January 08 2018
January 05 2018

Rescheduled: Overnight Sanitary Sewer Relocation at Brentcliffe Portal January 9th to 14th from 9:00 p.m. to 5:00 a.m.

Original Issue Date: October 24, 2017
Repost & Update Date: November 27 and December 8, 2017
Repost & Update (2) Date: January 5, 2018 

Eglinton Avenue East Lane Closure between Brentcliffe Road and Leslie Street

What Work is Taking Place? Read more »

January 04 2018

Chaplin and Avenue Construction Liaison Committee Meeting

The construction liaison committee meeting of Chaplin and Avenue Stations was held on January 3, 2018. You can see the presentation here:

Read more »

December 29 2017

Bell Utility Relocation at Kennedy Station

What Work Is Taking Place?

As part of construction of the future Kennedy Station, crews will be relocating Bell utilities in the vicinity of Kennedy Road and Eglinton Avenue East.  The work will be completed in three (3) stages (pictured below). Read more »

December 22 2017

Update on Works and Upcoming Traffic Changes at Mount Pleasant Station

Originally Published: December 22, 2017

Updated: January 08, 2018

What Work Is Taking Place?

Since Fall 2017, crews have been undertaking utility and support of excavation work at Mount Pleasant Station. Below is the status of work that has been completed and work that is still ongoing:

Complete:

  • Hydro vault work at the southeast corner of Mount Pleasant Road and Eglinton Avenue East.

Ongoing: Read more »

December 21 2017

Construction Notice - Forest Hill - Asphalt Work at Hilltop & Eglinton

WHAT WORK IS TAKING PLACE?

As part of the ongoing sewer work at Forest Hill Station, crews will be removing the road plates and asphalting.  While this work takes place, one lane of Eglinton Ave W will be closed in the vicinity of Eglinton Ave W between Hilltop Rd and Chiltern Hill Rd.

TIMING 

Thursday December 21, 2017

7:00 a.m. – 11:00 p.m.

WHAT TO EXPECT Read more »