March 19 2018

UPDATE: Overnight Water Shut-Off at Eglinton Station

Originally Published: March 16, 2018

Updated: March 19, 2018

What Work is Taking Place?

In order to prepare for construction of Eglinton Station, crews have relocated water mains and sewers at the Yonge-Eglinton intersection to allow for piling and excavation works. In order maintain water service for all properties adjacent piling and excavation activities, crews will be connecting a new temporary water main with existing building site service connections. The following properties will lose water service temporarily during the water connections: Read more »

March 19 2018

Support of Excavation Works (Shoring) for the Future Kennedy Station

Originally Published: March 19, 2018

Updated: April 5, 2018

What Work is Taking Place?

We are working steadily in the east on the Eglinton Crosstown. In early April, there will be drilling in the middle of the roadway (Eglinton Avenue East), as crews begin the support of excavation work (shoring) to construct a tunnel to the new Kennedy Station. Read more »

March 18 2018

Upcoming Traffic Changes at Kennedy Road and Eglinton Avenue East

Originally Published: March 18, 2018

Updated: April 5, 2018

What Work is Taking Place?

Starting as early as Friday, April 6, 2018, crews will start support of excavation work, also known as shoring, for the future Kennedy Station. As part of these works traffic staging at the intersection of Kennedy Road and Eglinton Avenue East will be changing.   Read more »

March 16 2018

Lane Impacts and Driveway Work at Leaside Station

WHAT WORK IS TAKING PLACE?

Work requiring the use of the eastbound lane between Bayview Avenue and 1750 Bayview Driveway will continue for the next one (1) to two (2) weeks. This work is required to support the completion of decking on the southwest corner.

Read more »

March 15 2018

Leaside & Laird Stations Construction Liaison Committee Meeting

The construction liaison committee meeting of Leaside and Laird Stations was held on March 14, 2018. You can see the presentation here:

Read more »

March 15 2018

Mining at Avenue Station - Both Station Entrances

What Work is Happening?

The Eglinton Crosstown includes a 10-kilometre underground portion, between Weston Road and Laird Drive, where 15 below-grade stations are under construction. Eleven will be built using a “cut-and cover” method and four, including Avenue Station, are going to be “mined.” 

Excavation of the Main Entrance at Avenue Station is nearing completion and mining will begin soon. Read more »

March 15 2018

Toronto Hydro Installation for Facility Services Building Construction at Eglinton Station

What Work is Taking Place?

As early as March 20, work will get underway to install new underground Toronto Hydro infrastructure that will replace the existing overhead cables, provide temporary power during construction of the Facility Services Building for the TTC Line 1 Subway system (pictured below) and new power connections for the same in the future. The existing overhead cables will be removed to facilitate the construction of the new building. Read more »

March 14 2018

Eglinton & Mount Pleasant Construction Liaison Committee Meeting

The construction liaison committee meeting of Eglinton and Mount Pleasant Stations was held on March 13, 2018. You can see the presentation here: