March 13 2018

75-Hour Weekend Work for GO Transit Improvements at Kennedy Station

Originally Published: March 13, 2018

Updated: March 15, 2018

Updated: March 16, 2018

Updated: March 20, 2018 Read more »

March 13 2018

Black Creek Drive Lane Closures

Updated March 13

WHAT WORK IS TAKING PLACE? Read more »

March 13 2018

Temporary Closure of Ionview Road

Originally Published: March 13, 2018

Updated: April 8, 2018

Updated: April 20, 2018

Updated: May 03, 2018

Updated: May 07, 2018

Updated: May 17, 2018

What Work is Taking Place?

As part of construction of the future Kennedy Station, crews will be relocating storm and sanitary utilities in the vicinity of Ionview Road and Eglinton Avenue East, including performing an east-west crossing across Ionview Road. Read more »

March 13 2018

Overnight Water Site Service Connections at Eglinton Station

What Work is Taking Place?

In order to prepare for construction of Eglinton Station, crews have relocated water mains and sewers at the Yonge-Eglinton intersection to allow for piling and excavation works. In order to complete the next stage of the work, crews will be connecting the new temporary main with the existing site service connections. The following properties may lose water service during the connections:

20, 30, 40, and 50 Eglinton Avenue East

 

Hours of Work Read more »

March 13 2018

Toronto Hydro Relocation Work at Cedarvale Station

What Work is Taking Place?

To accommodate upcoming shoring activities for the new Cedarvale LRT Station, crews will be relocating a Toronto hydro infrastructure from underground ducting to overhead cables. The work will involve trenching and removing the existing duct banks, and installing new overhead hydro cables. Read more »

March 12 2018

Shoring at Chaplin Station Main Entrance

WHAT WORK IS TAKING PLACE?

Support of excavation (or shoring) continues at Chaplin Station. At the Main Entrance site, located on the northeast corner of Chaplin and Eglinton, there are some piles that remain to be installed.

As early as Wednesday, March 14, crews will begin piling activities at the Main Entrance. The drill will cross Eglinton to the Main Entrance site as early as Monday, March 12.

TIMING  Read more »

March 09 2018

Overnight Road Repair Work Starting March 12 - Traffic Lane Reductions at Don Mills & Eglinton

What Work is Taking Place?

Ongoing road maintenance continues around the Don Mills Road and Eglinton Avenue East intersection. The rebuilding of catch basins on Eglinton Avenue East between the DVP and Don Mills Road will start on Monday, March 12, 2018 for approximately one week.

To minimize traffic disruption for the community, transit users and local businesses, this work is being done overnight.

Hours of Work Read more »

March 09 2018

Resumption of Storm Sewer Installation at Mount Pleasant Station

What Work is Taking Place?

In December 2018, crews began installation of a new storm sewer along the south side of Eglinton Avenue East.  Beginning March 8, storm sewer installation will resume.  The storm sewer will be installed using a hand-mining method whereby pipe is hydraulically pushed through the soil from the shafts at Taunton Road and Brownlow Avenue while soil is simultaneously removed.  Once the pipe installation is complete, connection work will be performed to connect the new storm sewer to the existing storm infrastructure. Read more »

March 08 2018

Chaplin and Avenue Construction Liaison Committee Meeting

The construction liaison committee meeting of Chaplin and Avenue Stations was held on March 7, 2018. You can see the presentation here: Read more »