November 24 2020

Notice of Water Shut-Off at Chaplin Station - November 26, 2020

What Work is Taking Place?

On Thursday November 26, 2020, crews will repair a water main located at the Tertiary Entrance site.  A water shut-off is required while this work takes place.  Water service will be restored upon completion of the work.

Water Shut-off Details:

November 24 2020

Cancellation: Fire Hydrant Removal at Eglinton Avenue East and Donlea Drive - November 19 – November 20, 2020

 

 

What Work is Taking Place?

*This work has been CANCELLED UNTIL FURTHER NOTICE as of November 24th, 2020*

From November 19 – November 20, 2020, crews will work to remove an abandoned fire hydrant at the north-east corner of Eglinton Avenue East and Donlea Drive. This work is expected to take place from 6:00 a.m. – 5:00 p.m. Read more »

November 23 2020

Laneway Closure at Chaplin Station - November 23, 2020

Laneway Closure at Chaplin Station - Nov 23, 2020

What Work is Taking Place?

On November 23, 2020, the Chaplin Crescent-Russell Hill Road laneway located south of Eglinton Avenue will be closed from 7:00 a.m. - 10:00 a.m. while crews perform telecommunication utility relocation at the Tertiary Entrance.

November 23 2020

Eglinton Station Construction Update - November 2020

 

 

What Work Is Taking Place?

Several construction activities are underway at Eglinton Station:  

Beneath Eglinton Avenue, crews are excavating the remaining soil and pouring concrete slabs at the platform level.  

November 22 2020

Sidewalk Construction at Eglinton Square

November 23, 2020

 

What Work is Taking Place?

November 19 2020

UPDATED: Temporary Traffic Configuration Change at Fairbank Station - November 27, 2020

Information updated as of November 26, 2020

 

What Work is Taking Place?

November 17 2020

Laird Station Overnight Backfilling Works - November 18 2020

What Work is Taking Place?

As early as November 18, 2020, crews will begin backfilling activities at the south west corner of Eglinton and Laird Drive. Work will take place between the hours of 9:00p.m. to 5:00 a.m. Monday to Saturday for a period of two (2) weeks.

 