Road Milling Works - Eglinton Avenue, Don Mills Road to Swift Drive
Looking for information related to a specific area?
Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).
- Allen Road
- Avenue Road
- Bathurst Street
- Bayview Avenue
- Bermondsey Road
- Birchmount Road
- Black Creek Drive
- Brentcliffe Road
- Caledonia Road
- Chaplin Crescent
- Don Mills Road
- Donlea Drive/Hanna Road
- Don Valley Parkway (DVP)
- Dufferin Street
- Ferrand Drive
- Ionview Road
- Keele Street
- Kennedy Road
- Laird Drive
- Leslie Street
- Lebovic Avenue
- Little Blvd.
- Mount Pleasant Road
- Oakwood Avenue
- Petman Avenue
- Pharmacy Avenue
- Victoria Park Avenue
- Warden Avenue
- Weston Road
- Wynford Drive
- Yonge Street
Road Milling Works - Eglinton Avenue East, Don Mills Road to Swift Drive
Monday, October 4 – Saturday, October 9, 2021
What Work is Taking Place?
In preparation for the upcoming final road restoration works, crews will perform road milling works on Eglinton Avenue East from Don Mills Road to Swift Drive. This work will begin as early as Monday, Monday, October 4, 2021 and continue through to Saturday, October 9, 2021. This work is expected to take place between 8:00 p.m - 6:00 a.m., with occasional accessory work taking place during regular work hours. Traffic in the intersection will be periodically reduced while this work takes place. Through-traffic in all directions and all turns will be maintained. For more information, please review the complete notice or visit www.thecrosstown.ca for more information.
What to Expect
Noise from construction activities including asphalt removals (milling) and asphalt paving. Access to all connecting streets and driveways will be maintained for the duration of this work. Traffic control personnel and/or a Paid Duty Officer will be present while this work takes place.
Traffic Impacts
- Traffic on Eglinton Avenue East from Don Mills Road to Swift Drive will be periodically reduced
Pedestrian Impacts
- There will be no changes to pedestrian routes
- There will be no changes to TTC stops
Hours of Work
- Monday, October 4 – Saturday, October 9, 2021
- This work is expected to take place between 8:00 p.m. to 6:00 a.m.