December 08 2017

Upcoming Toronto Hydro-Electric System Development for Eglinton Station

What Work is Taking Place?

To prepare for the construction of Eglinton Station, crews have been working to re-route existing hydro utilities in the vicinity of Eglinton Avenue and Yonge Street.  Read more »

December 08 2017

Cancelled: Overnight Sanitary Sewer Relocation for the Brentcliffe Portal Starting Friday, December 8 at 9:00 p.m.

Sanitary sewer relocation work on Eglinton Avenue East between Brentcliffe Road and Leslie Street has been cancelled due to weather. 


Updated: December 8, 2017
Previous Update Issued: November 27, 2017
Original Issue Date: October 24, 2017
Read more »

December 08 2017

Watermain Relocation between Kennedy Road and West of Midland Avenue

What Work is Taking Place?

Crews will begin the relocation and upgrading of an existing watermain on the north and south sides of Eglinton Avenue East, the North Service Road and the South Service Road from Kennedy Road to approximately west of Midland Avenue. In an effort to minimize disruption to local traffic and commuters, work will be performed in stages.   Read more »

December 07 2017

Updated: Early Morning Concrete Pours at the Brentcliffe Portal in December 2017

What Work is Taking Place?

Crews will be pouring the concrete foundation and roof slabs for the Brentcliffe Portal. Work will be conducted within the existing work zone located on Eglinton Avenue East between Brentcliffe Road and Leslie Street. Due to the large size of these concrete pours, work will start at 4:00 a.m. in order to reduce impact to traffic in the area. Read more »

December 07 2017

Bell Utility Relocations and Watermain Investigations for Leaside Station

What Work is Taking Place?

Beginning as early as December 11th, Bell utility relocations and watermain investigations will take place in the vicinity of Eglinton Avenue East and Bayview Avenue. Works are short duration and will begin within the existing work zone at the main entrance. Work taking place outside the existing work zone will occur on Eglinton Avenue, east of the main entrance. Read more »

December 06 2017

East At-Grade (Pharmacy Stop to Ionview Stop) and Kennedy Station Open House

Thank you for attending the open house about Kennedy Station and East At-Grade (Pharmacy Stop to Ionview Stop) on December 5, 2017. 

For those of you who missed it, the presentation is here: Read more »

December 06 2017

Watermain Lining at Avenue Station Secondary Entrance

Original Issue Date: December 4, 2017
Updated: December 6, 2017 

WATERMAIN LINING AT AVENUE STATION SECONDARY ENTRANCE

Properties 270 – 302 Eglinton Avenue West

WHAT WORK IS TAKING PLACE? Read more »