What's New?

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

 
Syndicate content
 
October 27 2017

Sanitary Sewer Work at Forest Hill Station

What Work is Taking Place?

Beginning as early as Saturday October 28, crews will be working in the vicinity of Eglinton Avenue West at Hilltop and Chiltern Hill Roads to address a blockage in the sanitary sewer system. 

Eglinton Avenue West will be reduced to one lane in each direction while this work takes place. Road closures of Chiltern Hill Road and Hilltop Road at Eglinton Avenue may be required.  Additional rolling lane closures may be required.

Hours of Work

  Read more »

October 27 2017

Overnight Watermain and Sanitary Installation at Kennedy Station

Originally Issued: October 27, 2017

Updated and Reissued: November 1, 2017

What Work is Taking Place? Read more »

October 26 2017

Cedarvale - Forest Hill Construction Liaison Committee Meeting

The construction liaison committee meeting of Cedarvale and Forest Hill stations was held on October 25, 2017. You can see the presentation here:

Read more »

October 25 2017

Avenue Station Construction Updates - October 25

CONSTRUCTION ACTIVITIES AT AVENUE ROAD

Construction activities outside the long-term set up continues to be active as we prepare for upcoming mining operations. These activities are happening during the daytime and nighttime, and overlap. Residents and businesses can expect to see the following daytime and nighttime work at various locations in the roadway or on the sidewalk.

THIS WEEK AT AVENUE STATION: Read more »

October 25 2017

Elevated Guideway Piling

 

Elevated Guideway & West Portal Read more »

October 24 2017

Allen Road - Short Duration Rolling Lane Reductions - October 27

What Work is Taking Place?

  • Crews need to complete surveying activities for centre lines on Allen Road from Eglinton Avenue West to the Aldburn Road Bridge.
  • For two hours, one in each direction (north and south), Allen Road will have rolling lane reductions.

Timing Read more »

October 24 2017

Overnight Sanitary Sewer Relocation for Brentcliffe Portal

What Work is Taking Place?

Crews will relocate an existing sanitary sewer line on Eglinton Avenue East between Brentcliffe Road and Leslie Street to support the upgrade of existing infrastructure at the future Brentcliffe Portal and Sunnybrook Park Stop. 

To minimize traffic disruption for the community, transit users and local businesses, this work is being done overnight. Paid Duty Police Officers will maintain safe traffic flow. Read more »

October 24 2017

Traffic Change at Latimer & Eglinton for Chaplin Station Construction

What Work is Taking Place?

Since spring 2016, crews have been performing utilities relocation and support of excavation (shoring) in the vicinity of Chaplin Crescent and Eglinton Avenue West.  

As early as October 28, 2017, the work zone configuration will change in order to begin shoring and utility work (hydro, sewer) on the north side of Eglinton, while work continues on the south side of Eglinton.  Read more »

October 24 2017

Early Morning Concrete Pour at Cedarvale Station for Crossover Track Roof Construction

WHAT WORK IS TAKING PLACE?

  • With the invert concrete slab now complete at the crossover track section east of Cedarvale Station, the next phase is pouring the roof slab. The roof slab will be poured in sections. 
  • Due to the large size of these concrete pours, work will start at 4AM in order to complete the pour during the daytime hours, avoiding late overnight work. 
  • The first pour was successfully completed on October 12.

TIMING Read more »

October 23 2017

Eglinton Lane Reduction for Cedarvale Station Utility Work

What Work is Taking Place?

  • To accommodate the continued utility works for Cedarvale Station, crews will reduce eastbound Eglinton Avenue from Park Hill Road to Allen Road to one lane to access two maintenance manholes.

Timing

  • The lane reduction is scheduled for October 23 – 27 from 10:00 AM to 3:00 PM daily to reduce impact on peak traffic hours.
  • Work may be delayed due to weather conditions or unforeseen circumstances.

What to Expect

  • Eglinton Avenue will be reduce