March 16 2018

Lane Impacts and Driveway Work at Leaside Station

WHAT WORK IS TAKING PLACE?

Work requiring the use of the eastbound lane between Bayview Avenue and 1750 Bayview Driveway will continue for the next one (1) to two (2) weeks. This work is required to support the completion of decking on the southwest corner.

Read more »

March 15 2018

Toronto Hydro Installation for Facility Services Building Construction at Eglinton Station

What Work is Taking Place?

As early as March 20, work will get underway to install new underground Toronto Hydro infrastructure that will replace the existing overhead cables, provide temporary power during construction of the Facility Services Building for the TTC Line 1 Subway system (pictured below) and new power connections for the same in the future. The existing overhead cables will be removed to facilitate the construction of the new building. Read more »

March 15 2018

Leaside & Laird Stations Construction Liaison Committee Meeting

The construction liaison committee meeting of Leaside and Laird Stations was held on March 14, 2018. You can see the presentation here:

Read more »

March 15 2018

Mining at Avenue Station - Both Station Entrances

What Work is Happening?

The Eglinton Crosstown includes a 10-kilometre underground portion, between Weston Road and Laird Drive, where 15 below-grade stations are under construction. Eleven will be built using a “cut-and cover” method and four, including Avenue Station, are going to be “mined.” 

Excavation of the Main Entrance at Avenue Station is nearing completion and mining will begin soon. Read more »

March 14 2018

Eglinton & Mount Pleasant Construction Liaison Committee Meeting

The construction liaison committee meeting of Eglinton and Mount Pleasant Stations was held on March 13, 2018. You can see the presentation here:

Read more »

March 13 2018

Toronto Hydro Relocation Work at Cedarvale Station

What Work is Taking Place?

To accommodate upcoming shoring activities for the new Cedarvale LRT Station, crews will be relocating a Toronto hydro infrastructure from underground ducting to overhead cables. The work will involve trenching and removing the existing duct banks, and installing new overhead hydro cables. Read more »

March 13 2018

75-Hour Weekend Work for GO Transit Improvements at Kennedy Station

Originally Published: March 13, 2018

Updated: March 15, 2018

Updated: March 16, 2018

Updated: March 20, 2018 Read more »

March 13 2018

Black Creek Drive Lane Closures

Updated March 13

WHAT WORK IS TAKING PLACE? Read more »