Tower Crane Removal at Chaplin Station’s Tertiary Entrance
Looking for information related to a specific area?
Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).
Choose an intersection (A to Z)
- Allen Road
- Avenue Road
- Bathurst Street
- Bayview Avenue
- Bermondsey Road
- Birchmount Road
- Black Creek Drive
- Brentcliffe Road
- Caledonia Road
- Chaplin Crescent
- Don Mills Road
- Donlea Drive/Hanna Road
- Don Valley Parkway (DVP)
- Dufferin Street
- Ferrand Drive
- Ionview Road
- Keele Street
- Kennedy Road
- Laird Drive
- Leslie Street
- Lebovic Avenue
- Little Blvd.
- Mount Pleasant Road
- Oakwood Avenue
- Petman Avenue
- Pharmacy Avenue
- Victoria Park Avenue
- Warden Avenue
- Weston Road
- Wynford Drive
- Yonge Street
January 12, 2022
WHAT WORK IS TAKING PLACE?
As early as Tuesday, January 18, 2022, crews at Chaplin Station will remove the tower crane from the Tertiary Entrance site. The crane removal is expected to start at 8:30 a.m. and take approximately eight (8) hours to complete. During this work, Chapin Crescent will remain closed between the Chaplin – Russel Hill Laneway and Eglinton Avenue West. Significant traffic and pedestrian changes will be in effect.
Please review the complete notice or visit www.thecrosstown.ca for more information.
WHAT TO EXPECT
Chaplin Crescent will remain closed between Eglinton Avenue West and the Chaplin-Russell Hill laneway; emergency service vehicles excepted. Truck staging on Chaplin Crescent can be expected. Use of a mobile crane within the laneway to remove the tower crane segments. Noise from construction equipment including transport trucks and a crane can be expected. Property access will be maintained. Expect delays while travelling through the intersection.
HOURS OF WORK
• As early as Tuesday January 18, 2022 starting at 8:30 a.m. for approximately eight (8) hours.
• Chaplin Crescent and the Chaplin-Russell Hill laneway will be closed on a 24-hour basis.
• This work may be rescheduled due to inclement weather and/or unforeseen circumstances.
TRAFFIC DETAILS
• Chaplin Crescent will be closed between Eglinton Avenue West and the Chaplin-Russell Hill laneway.
• The parking lot at 643 Eglinton Avenue West will be temporarily occupied during this work.
• To accommodate the TTC detour, on-street parking on Russell Hill and Tarlton Roads. will be prohibited for the duration of the closure.
PEDESTRIAN DETAILS
• The Chaplin-Russell Hill laneway will remain closed behind the Tertiary Entrance
• The north and east crosswalks will be maintained.
• The south crosswalk will be relocated further south on Chaplin Crescent.
TRANSIT INFORMATION
• TTC bus route 14 Glencairn will be on detour during this work, to accommodate the closure of Chaplin Crescent.
• Westbound buses will turn right onto Tarlton Road, left onto Eglinton Avenue West and continue north on Chaplin Crescent.
• Eastbound buses will turn left onto Eglinton Avenue West, right onto Russell Hill Road and continue south on Chaplin Crescent.
• For more information, visit www.ttc.ca