Tunnel Backfilling Brentcliffe Road to Laird Drive
Looking for information related to a specific area?
Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).
Choose an intersection (A to Z)
- Allen Road
- Avenue Road
- Bathurst Street
- Bayview Avenue
- Bermondsey Road
- Birchmount Road
- Black Creek Drive
- Brentcliffe Road
- Caledonia Road
- Chaplin Crescent
- Don Mills Road
- Donlea Drive/Hanna Road
- Don Valley Parkway (DVP)
- Dufferin Street
- Ferrand Drive
- Ionview Road
- Keele Street
- Kennedy Road
- Laird Drive
- Leslie Street
- Lebovic Avenue
- Little Blvd.
- Mount Pleasant Road
- Oakwood Avenue
- Petman Avenue
- Pharmacy Avenue
- Victoria Park Avenue
- Warden Avenue
- Weston Road
- Wynford Drive
- Yonge Street
October 5, 2017
What Work is Taking Place?
To support the ongoing mining works at the future Laird Station, a layer of backfill (granular material) will be added to the base of the existing tunnel from the Brentcliffe Portal to Laird Drive.
Backfill material will be stockpiled and then be pushed in to the tunnel at Brentcliffe Portal and inside the tunnels towards Laird Drive. Compaction of the material will occur inside of the tunnels.
Hours of Work
- Stockpiling will be carried on dayshift between 7am to 11pm.
- Work in the tunnels occurs on a 24 hour schedule.
- Work is expected to begin as soon as October 10, 2017 and take approximately three (3) weeks.
What to Expect
- Nearby properties may feel vibrations related to the compaction work however it is expected to be minimal due to the depth of the tunnels.
- Crews are monitoring noise and vibration during this work.
- Trucks will deliver material to the Brentcliffe site periodically throughout the day.
Traffic and Pedestrian Impacts
- There are no pedestrian or traffic related impacts for this work.