Upcoming Concrete Pour at Bayview Avenue and Eglinton Avenue East

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

 
April 8, 2021

 

Traffic Configuration

As early as Wednesday April 14, 2021 crews at Leaside Station will perform a concrete pour at the Main Entrance site. The concrete will form the roof of Leaside Station’s Main Entrance building. 

 

To perform this work safely, the sidewalk on the east side of Bayview Avenue, south of Eglinton Avenue East, will be temporarily closed during the pour. To ensure the integrity and continuity of the concrete, work will begin as early as 5:00 a.m. and take approximately fifteen (15) hours to complete. Traffic control personnel and/or a Paid Duty Officer will be present, while this work takes place.

 

What to Expect

 

Noise from construction equipment including concrete trucks and pumps can be expected. Please note that concrete trucks must remain running to allow for continuous turning of the mixer and to discharge concrete. Site lighting is required and will be positioned away from residential properties. Two concrete pumps will be set up within the work one. +7 concrete trucks are expected per hour. Expect delays while travelling through the intersection. 

 

 

Hours of Work

 

•    As early as Wednesday, April 14, 2021.

•    The pour will begin at approximately 5:00 a.m. and is expected to take fifteen (15) hours to complete. 

•    Work may be rescheduled due to inclement weather and/or unforeseen circumstances.

•    Extended construction hours are currently underway and will continue during this work. 

 

Traffic Details

 

•    No changes to the current traffic configuration are expected as a result of this work. 

 

Pedestrians Details

 

•    The sidewalk on the east side of Bayview Ave, south of Eglinton Ave E, will be closed while this work takes place.

•    Advance signage will be in place to direct pedestrians. 

 

Transit Information

•    Access to TTC will be maintained.

•    Please visit www.ttc.ca for more information. 

 