Update: 24-hour Construction at Avenue Station - March 2021
Looking for information related to a specific area?
Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).
- Allen Road
- Avenue Road
- Bathurst Street
- Bayview Avenue
- Bermondsey Road
- Birchmount Road
- Black Creek Drive
- Brentcliffe Road
- Caledonia Road
- Chaplin Crescent
- Don Mills Road
- Donlea Drive/Hanna Road
- Don Valley Parkway (DVP)
- Dufferin Street
- Ferrand Drive
- Ionview Road
- Keele Street
- Kennedy Road
- Laird Drive
- Leslie Street
- Lebovic Avenue
- Little Blvd.
- Mount Pleasant Road
- Oakwood Avenue
- Petman Avenue
- Pharmacy Avenue
- Victoria Park Avenue
- Warden Avenue
- Weston Road
- Wynford Drive
- Yonge Street
What Work is Taking Place?
Construction at Avenue Station takes place 24 hours Monday through Friday, and 7:00 a.m. - 7:00 p.m. on Saturday. The following activities are currently underway:
- Main Entrance Construction
Final lining and structural works are ongoing approximately 6 metres below surface level. This work includes installation of waterproofing, rebar, steel, conduits, and formwork. Concrete pours take place on a weekly basis. Each pour takes approximately 12-18 hours to complete. The Gantry crane remains in place at the Main Entrance to assist with lifting materials into the site. Works at the Main Entrance are expected to reach surface level in Summer 2021.
- Secondary Entrance Construction
Structural works, including steel framing, rebar and formwork installation. Crews are building and removing timber and steel molds using a mallet hammer. This activity is required to pour the concrete that forms the station walls and slabs. The work has reached surface level and is expected to continue until late April 2021.
- Station Box (beneath Eglinton Avenue)
Final lining of the cavern arches, concourse slabs, and headwalls. Final lining works include waterproofing, rebar, conduit, and formwork installation. Concrete works will continue through the entire station box through Summer 2021. The supports for Overhead Catenary System (OCS) are being installed above track level. The OCS will provide operational power to the Light Rail Vehicles (LRVs).
Please review "What to Expect" or visit www.thecrosstown.ca for more information.
What to Expect
Noise from construction activity including, trucks, hammering, crane, and material loading can be expected during the day, evening and overnight periods. Expect delays while travelling through the intersection.
HOURS OF WORK
- Construction at Avenue Station takes place on a 24-hour basis Monday through Friday, and Saturdays between 7:00 a.m. – 7:00 p.m.
- Occasionally, crews will be required to work overnight through the weekends to complete critical activities
- Work may be delayed or rescheduled due to inclement weather or unforeseen circumstances.
TRAFFIC & PEDESTRIAN DETAILS
- No changes to the current traffic configuration and pedestrian routes are expected as a result of this work
TRANSIT INFORMATION
- Access to TTC will be maintained at all times