UPDATE: Concrete Pour at Mount Pleasant Station Wednesday, June 19, 2019
Looking for information related to a specific area?
Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).
Choose an intersection (A to Z)
- Allen Road
- Avenue Road
- Bathurst Street
- Bayview Avenue
- Bermondsey Road
- Birchmount Road
- Black Creek Drive
- Brentcliffe Road
- Caledonia Road
- Chaplin Crescent
- Don Mills Road
- Donlea Drive/Hanna Road
- Don Valley Parkway (DVP)
- Dufferin Street
- Ferrand Drive
- Ionview Road
- Keele Street
- Kennedy Road
- Laird Drive
- Leslie Street
- Lebovic Avenue
- Little Blvd.
- Mount Pleasant Road
- Oakwood Avenue
- Petman Avenue
- Pharmacy Avenue
- Victoria Park Avenue
- Warden Avenue
- Weston Road
- Wynford Drive
- Yonge Street
June 17, 2019
On Wednesday, June 19th, crews will perform a concrete pour in the southeast work zone at Mt Pleasant Road and Eglinton Avenue. The concrete will form part of the roof of Mount Pleasant Station. A concrete pump will be set up within the work zone, and concrete trucks will stage on the south side of Eglinton Avenue, east of Taunton Road, while this work takes place. To ensure the integrity and continuity of the pour, work will begin early at 5:00 a.m.
Details
- Wednesday, June 19th, beginning at 5:00 a.m. for approximately eight (8) hours
- In the event of inclement weather or delay, this activity will be rescheduled
Construction Staging
What to Expect
- One concrete pump will be stationed in the east end of the southeast work zone
- 8+ concrete trucks are expected per hour
- Concrete trucks will stage within the work zone and on the south side of Eglinton Ave, east of Taunton Rd
- Noise from construction activity can be expected
Disponible en francais