June 23, 2020

 

What Work is Taking Place?

Deep excavation has been underway at Mount Pleasant Station since February 2020.  Crews are currently excavating the station box beneath Eglinton Avenue. Soil is being removed through the Secondary Entrance located on the north side of Eglinton Avenue, between Mount Pleasant Road and Rawlinson Avenue. At the beginning of June, crews started to demolish the tunnels beneath Eglinton Avenue to make way for construction of the station underground. 

On Tuesday, June 23, 2020, crews will work overnight to remove and haul the broken tunnel segments from the station box. Using a crane, the concrete tunnel encasement will be loaded onto a truck and hauled from the Main Entrance to an off-site facility.  

 

Hours of Work 

Tuesday, June 23, 2020 

Crews will work overnight to remove and haul the broken tunnel segments from the Main Entrance site

This work may be longer or shorter than expected 

 

Work Area Map

 

What to Expect

Hauling trucks entering and exiting the Main Entrance site. 

Dump trucks will stage on Eglinton Avenue and within the Main Entrance site 

Overnight noise and site lighting can be expected.

Property access will be maintained.

 

Traffic and Pedestrian Details

The current traffic configuration and pedestrian routes at Mt Pleasant Station are expected to remain in place for the duration this work.

 

Travelling Smart during Construction

Travel delays are expected with the Crosstown construction. Please allow extra time for your journey. Traffic will be extra heavy at peak periods during the Crosstown construction. When possible, please travel during the off-peak period between 10 a.m. and 3 p.m. 

 

Sign up for e-mail updates at www.thecrosstown.ca/sign-up or download the Crosstown traffic app to get real-time traffic and transit information for the Eglinton corridor. 

 

Thank you for your patience as we work to build this important project.

Please support your local business during construction.

 

Disponible en francais