Update: Notice of Possible Water Pressure Change - Extended to March 5, 2021

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

 
February 26, 2021

Possible Water Pressure Change Catchment Area - Extended to March 5, 2021

What Work is Taking Place?

On Monday February 8, 2021 crews began work on the 600 mm water main at the intersection of Chaplin Crescent and Eglinton Avenue West.  This work has been extended to Friday March 5, 2021.  Properties in the pictured catchment area may experience periods of lower than usual water pressure as a result of this work. This is not a water shut-off notice.  Water service will be maintained but lower water pressure may be experienced.

Water Pressure Change Details:

  • Wednesday February 8 to Friday March 5, 2021
  • Properties in the pictured catchment area may experience lower than usual water pressure

What to Expect

Properties in the pictured catchment area (above) may experience lower than usual water pressure.  For more information on this work, visit www.thecrosstown.ca.

HOURS OF WORK

  • Duration of this work has been extended to March 5, 2021

UTILITY INTERRUPTIONS

  • Properties within the catchment area between Chiltern Hill Road to Spadina Road and Eglinton Avenue West to Ava Road may be affected
  • This is not a water shut-off
  • Water service will be maintained but lower than usual water pressure may be expected

TRAFFIC & PEDESTRIAN DETAILS

  • There are no changes to traffic configuration or pedestrian routing associated with this work

TRANSIT INFORMATION

  • No change to TTC required for this work
  • Please visit www.ttc.ca for more transit information

 